Vietnam.vn - Nền tảng quảng bá Việt Nam

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion.

More than three months after construction resumed following years of inactivity, the Phuoc Khanh bridge – the final bottleneck of the Ben Luc - Long Thanh expressway – is accelerating towards completion.

VTC NewsVTC News17/12/2025

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 1

According to VTC News reporters, after years of interrupted construction, the Phuoc Khanh bridge section on the Ben Luc - Long Thanh expressway is now receiving concentrated resources from relevant units to accelerate progress. According to the plan, this key project is expected to be completed in about 15 months, contributing to resolving a crucial bottleneck on the entire expressway.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 2

Construction of the Phuoc Khanh bridge project restarted in early May 2025, after the completion of the selection process for a new contractor. The project is currently being implemented under package J3-1, undertaking the remaining work of the previous J3 package.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 3

Previously, the Phước Khánh bridge construction package, contracted by the Vietnam Expressway Investment and Development Corporation (VEC) with the Sumitomo Mitsui - Cienco 4 consortium, commenced in January 2016. However, due to difficulties in capital allocation and loan agreement extensions, the project was temporarily suspended in 2020, having completed over 80% of the work. After nearly five years of stagnation, this package has been restarted with a new contractor to continue construction.

The final 'bottleneck' of the Ben Luc - Long Thanh expressway accelerates towards completion - 4

Observations at the construction site show that pier P16 on the Nhon Trach ( Dong Nai ) side has risen high with 6 bundles of stay cables installed, marking an important step in the construction of Phuoc Khanh bridge and demonstrating the rapid pace of implementation after the project was restarted.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 5

Meanwhile, the main pier P15 on the Can Gio side has also completed the construction of the 5th cable-stayed bundle and is continuing to deploy the 6th bundle, indicating that the construction progress of key components of the Phuoc Khanh bridge is being accelerated on both sides of the project.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 6

At both ends of the bridge, in the Can Gio and Nhon Trach areas, the access roads to the bridge have been largely completed, including the asphalt paving, installation of railings and lighting systems, contributing to the synchronization of infrastructure and creating favorable conditions for subsequent construction phases.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 7

The Phuoc Khanh Bridge is one of the two largest bridges on the Ben Luc - Long Thanh expressway, spanning the Long Tau River and connecting Can Gio (Ho Chi Minh City) with Nhon Trach (Dong Nai province). It plays a crucial role in ensuring smooth inter-regional traffic flow. Designed as a cable-stayed bridge, it is over 3 km long, nearly 22 m wide, and has a clearance of 55 m – the highest among current bridges in Vietnam.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 8

The joint venture between Bac Trung Nam Infrastructure Construction Joint Stock Company and Freyssinet Vietnam Co., Ltd. was awarded the contract, worth over 635 billion VND; the expected construction time is 450 days.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 9

The restart of the Phuoc Khanh bridge construction project is considered a crucial step towards connecting the entire Ben Luc - Long Thanh expressway. Currently, the remaining construction packages along the entire route have been basically completed, and many sections have been put into operation.

The final 'bottleneck' of the Ben Luc - Long Thanh expressway accelerates towards completion - 10

Construction began in 2014 on the Ben Luc – Long Thanh expressway project, with a total length of nearly 58 km, passing through the provinces and cities of Tay Ninh , Ho Chi Minh City, and Dong Nai province. The initial investment was 31,300 billion VND, which has now been reduced to 29,587 billion VND.

The final bottleneck on the Ben Luc - Long Thanh expressway accelerates towards completion - 11

The route is designed with 4 lanes for traffic and 2 emergency stopping lanes, with a maximum operating speed of 100 km/h. It serves as the largest expressway project in the Southern region, connecting the Eastern and Southwestern regions, and contributing to traffic diversion and reducing congestion in Ho Chi Minh City's inner city. However, due to obstacles related to investment mechanisms and policies, and difficulties in securing funding, the project has experienced numerous delays.

Luong Y

Source: https://vtcnews.vn/nut-that-cuoi-cung-cao-toc-ben-luc-long-thanh-tang-toc-ve-dich-ar993479.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

A close-up view of the workshop making the LED star for Notre Dame Cathedral.
The 8-meter-tall Christmas star illuminating Notre Dame Cathedral in Ho Chi Minh City is particularly striking.
Huynh Nhu makes history at the SEA Games: A record that will be very difficult to break.
The stunning church on Highway 51 lit up for Christmas, attracting the attention of everyone passing by.

Same author

Heritage

Figure

Enterprise

Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.

News

Political System

Destination

Product