The Hong Linh Town Square project ( Ha Tinh ) has completed 70% of the work volume. Contractors are urgently speeding up the progress, striving to complete phase 1 ahead of schedule.
VIDEO : Bustling at the construction site of Hong Linh Town Square, phase 1
The Hong Linh Town Square project, invested by the Town People's Committee, is built in Bac Hong Ward. Phase 1 of the project is being implemented on an area of over 3.4 hectares with a total investment of 67 billion VND.
Construction started in January 2023, the project is identified as an important project contributing to the completion of the infrastructure system, completing the criteria for building the town to reach the level of a type III urban area. After 9 months of construction, the project has reached 70% of the total workload. The project items have been completed such as: leveling the ground with a total area of over 34 hectares...
...green tree system...
... power supply and lighting system for the square.
These days, taking advantage of the sunny weather, the construction unit is focusing on completing the traffic system of 4 routes with a total length of 999m...
... paving the square area.
Contractor for construction of sports complex and parking lot with an area of nearly 4,000m2
The Square area with logo and stage is being focused on by the contractor to ensure progress, completing nearly 70% of the volume.
Mr. Le Van Thanh - Technical Officer of Dai Phong Construction and Trading Consulting Co., Ltd. - one of the three contractors undertaking the construction of the project said: "The unit is focusing on completing items such as traffic system, logo, stage, internal yard and parking lot. Striving to complete the project by December 30, 2023, 8 months ahead of schedule."
Mr. Nguyen Cong Thien - Director of Hong Linh Town Construction Investment Project Management Board said: "The unit is continuing to direct contractors to implement the remaining items to complete the project. With the current construction progress, the goal of completing phase 1 of Hong Linh Town Square and handing it over 8 months ahead of schedule is completely feasible."
Nam Giang