Overview of the working session.
At the working session, reporting to the delegation on the progress of the Project, Mr. Le Ba Quy, Director of Nhon Trach 3 and 4 Power Project Management Board, said that up to now, the completed volume of the EPC Contract is estimated at about 94%. The Power Project Management Board (PVPP) and the Electricity Trading Company (EVNEPTC) signed the Power Purchase Agreement for the testing phase of Nhon Trach 3 Power Plant on May 27, 2024. PV Power and PV GAS have basically completed negotiations on the terms and contents of the GSA Contract, and are expected to sign the contract in the fourth quarter of 2024.
Mr. Le Ba Quy, Director of Nhon Trach 3 and 4 Power Project Management Board reported on the project progress.
Based on the updated progress until the end of August 2024 of the EPC contractor, the testing work of each plant is expected to be carried out within 178 days. Specifically, Nhon Trach 3 Power Plant is expected to start from the first ignition progress milestone on October 15, 2024, then test the guaranteed operating parameters, run reliably and operate commercially in April 2025. Nhon Trach 4 Power Plant will start from the first ignition progress milestone on December 22, 2024, test the guaranteed operating parameters, run reliably and operate commercially in July 2025.
Nhon Trach 3 and Nhon Trach 4 Power Plant Project is one of the important power source development projects, which is of great interest, monitored and directed by the Government, ministries and branches with urgent progress requirements. Therefore, to ensure the overall progress of the Project, PV Power recommends that the Group consult with the People's Committee of Dong Nai province to direct Tin Nghia Corporation to soon sign a land lease contract for the remaining 6.4 ha of the Project and sign a wastewater treatment contract for the Project to avoid affecting the progress of the trial run and applying for an environmental license; consult with Vietnam Electricity Group (EVN) to speed up the construction of the 500 kV transmission line projects of Nhon Trach 4 Power Plant - Phu My - Nha Be branch to connect, supply electricity for trial run and release the capacity of Nhon Trach 4 Power Plant;...
Petrovietnam General Director Le Ngoc Son and the working group inspected the project progress.
Attending the meeting, Petrovietnam Deputy General Director Phan Tu Giang and representatives of PV Power, Lilama, Samsung C&T, and PV GAS gave opinions and solutions to overcome current difficulties, as well as prepare for the first ignition in October 2024 of Nhon Trach 3 Power Plant, thereby completing the next steps, in time for commercial operation in April 2025.
Speaking at the meeting, Petrovietnam General Director Le Ngoc Son highly appreciated the efforts of all parties to speed up the project's progress and complete the steps to prepare for the first ignition of Nhon Trach 3 Power Plant.
Petrovietnam General Director Le Ngoc Son gave a speech at the meeting.
Petrovietnam General Director emphasized that Petrovietnam has taken a step forward in implementing the LNG sector, the LNG gas project chain. This is the first project chain that Petrovietnam has implemented according to the policy of Conclusion 76-KL/TW of the Politburo . To successfully implement this orientation, as well as the LNG Gas - Power chain, the Nhon Trach 3 and 4 Power Project is a very important link. Therefore, the Group and related units will focus on resolving difficulties in the spirit of "One team, one goal", soon putting the project into operation according to the set schedule.
Nguyen Hien