ACV receives 100% of the land for construction of Long Thanh airport

Người Đưa TinNgười Đưa Tin03/11/2023


According to information from Vietnam Airports Corporation (ACV), the unit has received 100% of the clean site to construct Long Thanh International Airport phase 1.

Specifically, ACV has received the full handover of 2,532 hectares of land from Dong Nai province, including 1,810 hectares in the project construction area and 722 hectares in the land reserve area.

However, ACV said that the two traffic routes connecting to the project have not yet been able to completely hand over the land when route 1 has handed over 60.28/66.45ha (reaching 90.7%); route 2 has handed over 20.50/59.68ha (reaching 34.3%).

Therefore, ACV requested the locality to speed up the site clearance and handover of the remaining area to avoid the situation of "rice and beans", affecting the construction progress of the project.

ACV also confirmed that it has prepared funds for site clearance of about 1,600 billion VND and will immediately transfer them to the locality when there is a payment decision approved by the Long Thanh District People's Committee for each household.

Event - ACV receives 100% handover of site for construction of Long Thanh airport

Long Thanh International Airport project has a total investment of about 336,630 billion VND, divided into three phases.

According to ACV's report, as of October 2023, the total actual volume of excavation and leveling has been about 102 million m3 out of a total of 115 million m3, reaching over 88% of the total construction volume. In particular, the leveling work of priority areas for handover to the construction of the main structure has been completed, meeting the key progress of 15 months as directed by the Government and the Ministry of Transport .

In addition, the runway, taxiway, aircraft parking areas and areas arranged for component projects 1, 2, 4 have been completed according to the plan, ensuring synchronous construction of passenger terminal, runway, taxiway, and aircraft parking items.

Long Thanh International Airport project has a total investment of about 336,630 billion VND, divided into 3 phases.

Phase 1: Construction of a runway, passenger terminal and auxiliary facilities with a capacity of 25 million passengers/year. According to the plan, phase 1 of the project is expected to be completed and put into operation in 2026.

Phase 2: The airport will build an additional open-configuration runway and terminal to reach a capacity of 50 million passengers/year.

Phase 3: Complete the remaining items so that the airport can reach a capacity of 100 million passengers/year and become the largest airport in Vietnam in the future and aim to become one of the busiest transit airports in the region .



Source

Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product