According to the Department of Construction of An Giang province, up to now, the province has basically completed the work of adjusting and supplementing key plans (issued the Decision to adjust the Planning of Kien Giang province (before the merger) for the period 2021-2030, with a vision to 2050; approved the local adjustment of the Master Plan of Phu Quoc special economic zone, An Giang province to 2040), added 23 locations to build projects serving the APEC Conference (13 locations) and other projects for the sustainable development of Phu Quoc in the coming time (10 locations).
The planning work is carried out synchronously, in accordance with legal regulations, ensuring inheritance, connectivity and feasibility, serving as a foundation for implementing key investment projects serving APEC 2027 and promoting sustainable socio -economic development for Phu Quoc Special Zone and An Giang province in the long term.
![]() |
| On September 24, 2025, the People's Committee of An Giang province simultaneously started construction and launched 10 projects to serve the APEC 2027 Conference. |
Regarding the progress of implementing 21 projects serving the APEC Conference (including 10 public investment projects and 11 investment projects under the public-private partnership (PPP) and business investment method), according to the People's Committee of Giang province, as of October 31, 2025, for 10 public investment projects, 8/10 projects have been approved for project investment and selected contractors and are under construction, including: Project of building embankments and leveling the ground for the construction of the APEC Conference Center and functional works, disbursed 396,874/670,085 million VND, reaching 59.23%.
The project to underground technical infrastructure in An Thoi area has disbursed 114,044/185,000 million VND, accounting for 61.54%.
The project to underground technical infrastructure in Duong Dong area has disbursed 155,224/232,000 million VND, reaching 66.88%.
APEC Avenue project has disbursed 124,323/294,040 million VND, reaching 42.28%.
Project to invest in technical infrastructure, digital transformation to build a smart monitoring and operating center to comprehensively manage Phu Quoc city.
Provincial Road Project DT.975 (Section from DT.973 - Phu Quoc Airport - DT.975 - DT.973), has disbursed 313,388/698,000 million VND, reaching 44.9%
Cua Can Lake Project, disbursed 225,766/285,541 million VND, reaching 79.07%.
The resettlement area project group includes 4 component projects. Of which, the An Thoi resettlement area component project has approved the project, approved the contractor selection results, signed the construction contract and started the project on September 24, 2025. The remaining three resettlement area component projects include: Cua Can Lake Resettlement Area, Suoi Lon Lake Resettlement Area and Ham Ninh Resettlement Area, requesting the People's Committee of Phu Quoc Special Zone to urgently complete the procedures to have a basis for advance investment capital according to the Emergency Order.
For the remaining 2/10 projects, including: The Duong Dong 2 Lake Project has been approved by the Provincial People's Committee in Decision No. 1732/QD-UBND dated October 30, 2025, approving the zoning plan of the Duong Dong 2 Lake Area, Phu Quoc Special Zone, An Giang Province, at a scale of 1/2000. The Urban Railway Line Project, Section 1, has been approved by the An Giang Provincial People's Council in its investment policy in Resolution No. 40/NQ-HDND dated October 24, 2025, with a total preliminary investment of nearly VND 9,000 billion (excluding interest).
Regarding the progress of 11 investment projects under the public-private partnership (PPP) and business investment methods, up to now, 7 projects have selected project investors and 4 projects are in the process of selecting investors.
Of which, 7/11 projects have selected project investors including: Phu Quoc International Airport expansion investment project, investor is Sun Airport Joint Stock Company (with total investment capital of 21,998 billion VND, project operation period is 70 years).
Mixed Urban Area Project - Bai Dat Do, investor is Phu Quoc Sun Company Limited (with total investment capital of 64,000 billion VND, project operation period is 70 years).
Ong Quan Mountain Eco-tourism Mixed Urban Area Project, investor is Phu Quoc Sun Company Limited (with total investment capital of 5,550 billion VND, project operation period is 70 years).
Cua Can Lake Water Plant Project (total investment capital of 556 billion VND); Bai Bon Domestic Solid Waste Treatment Plant Project (total investment capital of 382 billion VND); An Thoi Domestic Solid Waste Treatment Plant Project (total investment capital of 140 billion VND) have investors being Binh Duong Water - Environment Corporation Joint Stock Company.
The investor of Bai Bon Waste-to-Energy Plant project is a joint venture between GREENITY Hau Giang LLC - Tri Viet Energy LLC (total investment capital of 300 billion VND).
4/11 projects are in the process of selecting investors, including 3 projects that have approved investment policies and plans for selecting investors in special cases, currently issuing invitations for interest (Duong Dong Centralized Wastewater Treatment Plant project, An Thoi Centralized Wastewater Treatment Plant project, Duong Dong 2 Water Plant) and 1 project is in the process of implementing procedures for approving investment policies and selecting investors (APEC Conference Center).
For the remaining projects, the province will urgently complete, ensure project approval and start construction in November 2025.
Source: https://baodautu.vn/an-giang-sap-tiep-tuc-khoi-cong-loat-du-an-phuc-vu-hoi-nghi-apec-2027-d431235.html