Successfully energized the 500kV Monsoon – Thanh My transmission line project to serve electricity import from Laos

Báo An ninh Thủ đôBáo An ninh Thủ đô24/01/2025


ANTD.VN - Power Project Management Board 2 (under Vietnam Electricity Group - EVN) said that at 22:43 on January 23, 2025, the 500kV Monsoon - Thanh My transmission line project (section in Vietnam) was successfully energized.

Đường dây 500 kV Monsoon- Thạnh Mỹ thi công trên địa hình hiểm trở, phức tạp

The 500 kV Monsoon-Thanh My power line is being constructed in rugged and complex terrain.

This is a key transmission grid project, serving the import of electricity from the Monsoon wind power plant (in Laos) to Vietnam, adding 600MW of electricity to the national power system in the 2024-2025 period.

The 500 kV Monsoon - Thanh My transmission line project (section in Vietnam) is invested by Vietnam Electricity Group (EVN), and Power Project Management Board 2 (EVNPMB2) is assigned as the investor's representative.

The part of the project located in Vietnam is built in Nam Giang district, Quang Nam province with a length of about 44.71 km, the total investment of the project is more than 1,100 billion VND.

This is a double-circuit transmission line project, connecting the Monsoon Wind Power Plant complex (in Laos) to the Thanh My 500 kV Substation in Quang Nam province.

The project was started on September 30, 2023, overcoming many difficulties and challenges in converting forest use purposes, site clearance, difficult mountainous terrain plus harsh weather in the area, but thanks to the determination of the construction units on the site and the strong direction of EVN/EVNPMB2, the project has completed the work according to the approved design with the volume of 90/90 concrete foundation positions completed, 90/90 steel columns completed and 28/28 anchorage spaces completed.

The project part in Vietnam was completed 40 days ahead of the power generation milestone of the Monsoon wind power project (in Laos, expected to be completed in early March 2025).

The 500kV Monsoon - Thanh My transmission line has the capacity to transmit a maximum capacity of up to about 2,500MW, contributing to improving the operational capacity of the national power system through importing electricity from Laos.

In the near future, after the Monsoon wind power plant project (Laos side) is completed, this power line project will receive imported electricity from Laos with a capacity of 600MW, with an expected average annual electricity output of about 1.7 billion kWh.



Source: https://www.anninhthudo.vn/dong-dien-thanh-cong-du-an-duong-day-500kv-monsoon-thanh-my-phuc-vu-nhap-khau-dien-tu-lao-post601973.antd

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC