Many contractors on the Hoai Nhon - Quy Nhon expressway are simultaneously paving the road surface. Other contractors are mobilizing manpower and machinery to speed up construction, especially after the inspection by Deputy Minister of Construction Nguyen Viet Hung.
Other contractors on the Hoai Nhon - Quy Nhon Expressway Project are also mobilizing machinery and human resources, racing against time to complete the embankment work and soon proceed with asphalt paving. According to Project Management Board 85, currently the entire project has carried out R25 hollow asphalt concrete mixture for more than 31/70km, reaching more than 45%, and C19 asphalt concrete for more than 13km, reaching 19.25%. The project's output exceeds the set schedule.
Source: https://www.baogiaothong.vn/dong-loat-tham-nhua-cao-toc-hoai-nhon-quy-nhon-192250314173659923.htm