The nearly 690 billion VND multi-level interchange project is rushing to completion.

Người Đưa TinNgười Đưa Tin05/04/2024


Visiting the construction site of the multi-level interchange project at the intersection of Ton Duc Thang Street, Mang Nuoc Road, and National Highway 5 (Multi-level Interchange Project) in An Dong commune, An Duong district, Hai Phong city, in early April 2024, one could see a bustling and busy atmosphere. The construction contractor was concentrating machinery, equipment, and personnel to complete the final items in order to bring the project to completion as soon as possible.

With a total investment of nearly 690 billion VND from the local budget, the multi-level interchange project is one of the key transportation projects of Hai Phong City. The project is expected to eliminate traffic congestion hotspots and high-risk traffic accidents on National Highway 5, while also completing the transportation system of the port city.

Real Estate - Hai Phong: The nearly 690 billion VND multi-level interchange project is rushing to completion.

The construction contractor is completing the final stages of the multi-level interchange project in An Duong district, Hai Phong city.

According to information from the Hai Phong Traffic Construction Investment Project Management Board, the multi-level intersection project was approved by the Hai Phong City People's Committee in Decision No. 2112/QD-UBND dated July 1, 2022. The unit assigned to act as the investor's representative is the Hai Phong City People's Committee.

The multi-level interchange project commenced on January 7, 2023, and is expected to be completed and put into operation in July 2024. The contractor is a consortium of Khang Nguyen Infrastructure Construction Investment Joint Stock Company, Bridge 14 Joint Stock Company, and Phuc Loc Group Joint Stock Company.

During the project's construction, the contractor encountered numerous difficulties, primarily related to land clearance. As of early April 2024, 13 households whose land was to be acquired for the project had yet to hand over the land. In addition, construction faced many obstacles due to the limited space and the need to maintain traffic safety while carrying out the work.

Real Estate - Hai Phong: The nearly 690 billion VND multi-level intersection project is rushing to completion (Figure 2).

The overpass section of the multi-level intersection project in An Duong district, Hai Phong city, is basically complete.

To resolve difficulties and obstacles and help the contractor ensure the project's progress, the Hai Phong Department of Transport has issued directives on traffic diversion to limit vehicle traffic in the project area. Leaders of the Hai Phong City People's Committee have repeatedly inspected the site and requested the An Duong district government to be decisive in land clearance work.

Thanks to the aforementioned support and assistance, along with the contractor's efforts to overcome difficulties, the overpass section along National Highway 5 of the project was basically completed by April 5th. Currently, the contractor is painting the hard median strip, planting flowers to create a landscape...

To facilitate the construction of the branch road and interchange under the bridge, the Hai Phong Investment and Construction Project Management Board for Transportation Works issued Document No. 331/BQL-DA2 requesting the Department of Transportation to organize temporary traffic diversion from April 5th.

At the same time, we request that the People's Committee of An Duong District, Hai Phong City, direct relevant units, departments, and divisions to resolve all outstanding issues and hand over the entire site to the construction contractor before April 10th.

Real Estate - Hai Phong: The nearly 690 billion VND multi-level interchange project is rushing to completion (Figure 3).

The multi-level interchange project is expected to eliminate traffic "black spots" on National Highway 5 in An Duong district, Hai Phong city.

According to information from the Hai Phong Transport Construction Investment Project Management Board, the project was scheduled for completion in July 2024, as per the contract. However, based on the actual situation, the multi-level interchange project is expected to be completed and put into use in May 2024, coinciding with the 69th anniversary of the liberation of Hai Phong .

The project to construct a multi-level interchange at the intersection of Ton Duc Thang Street, Mang Nuoc Road, and National Highway 5 in An Dong commune, An Duong district, Hai Phong city, includes the following items: Construction of a flyover bridge in the direction of National Highway 5 - Nguyen Van Linh Road with a length of 285 m and a width of 19.5 m, and retaining walls for the approach roads at both ends of the bridge with a length of 200 m.

The roundabout under the bridge has four access roads on either side of the overpass, as well as roads connecting to the South Binh Bridge intersection, Ton Duc Thang Street, the planned Ring Road 2, and Mang Nuoc Street, linking to and from the central roundabout. The access roads on either side of the intersection have a cross-section of 9.5 m each, including a 7.5 m wide road surface and a 2 m wide sidewalk, gradually tapering to connect to the existing roads.



Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.
The unforgettable beauty of shooting 'hot girl' Phi Thanh Thao at the SEA Games 33
Hanoi's churches are brilliantly lit, and the Christmas atmosphere fills the streets.
Young people are enjoying taking photos and checking in at places where it looks like "snow is falling" in Ho Chi Minh City.

Same author

Heritage

Figure

Enterprise

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree

News

Political System

Destination

Product