Ho Chi Minh Road through rubber forest in Binh Duong opens to traffic on April 30

On February 22, information from the Ho Chi Minh Road Project Management Board said that the Ho Chi Minh Road project, Chon Thanh - Duc Hoa section (through Binh Duong) will be technically opened to traffic on April 30 this year.

Báo Thanh niênBáo Thanh niên22/02/2025

According to the Ho Chi Minh Road Project Management Board, the section passing through Binh Duong is 31 km long from Km10+00 (bordering Binh Phuoc province) to Km 41+150 (bordering Saigon River) via Thanh An bridge (Dau Tieng district, Binh Duong) connecting Binh Duong with Tay Ninh.

Ho Chi Minh Road through Binh Duong passes through vast rubber forests

PHOTO: DO TRUONG

The Ho Chi Minh Highway section through Binh Duong is designed to be a 6-lane highway with a design speed of 100 km/h. The first phase is invested in construction with a scale of 2 lanes, and in the future will continue to expand according to the development needs of the region.

In the first phase, the road is designed with 2 lanes and will be expanded according to development needs.

PHOTO: DO TRUONG

Up to now, the construction unit has basically completed the ground foundation and carried out the construction of the road surface foundation reaching 28/31 km; and the asphalt pavement construction reaching 19/31 km.

A section of road with completed road surface foundation

PHOTO: DO TRUONG

There are 6 bridges along the route, the largest of which is Thanh An Bridge across the Saigon River, over 600m long with 12 7m high clearance piers. The cantilever section is currently under construction, expected to be completed in February 2025.

Thanh An Bridge across the Saigon River

PHOTO: DO TRUONG

Phuoc Hoa Canal Bridge, Ba Tu Bridge and Suoi Tre Bridge have completed the bridge deck construction; Cay Truong Bridge and Thi Tinh Bridge have completed the lower part and girder launching.

Ba Tu Bridge has completed the bridge deck construction.

PHOTO: DO TRUONG

To date, the contractor has completed 70% of the contract volume, determined to have technical vehicles on April 30 and complete the project in August 2025, shortening the construction time by about 4 months compared to the contract.

Ho Chi Minh road through Binh Duong is expected to be technically open to traffic on April 30.

PHOTO: DO TRUONG

Previously, Mr. Nguyen Van Loi, Secretary of Binh Duong Provincial Party Committee, inspected and directed the work of clearing and handing over the site for road construction.


Binh Duong Provincial leaders propose to complete site handover in March 2025

PHOTO: DO TRUONG

Accordingly, the Ho Chi Minh road section through Binh Duong still has 7 points that are stuck in site clearance in Dau Tieng and Bau Bang districts. Mr. Nguyen Van Loi has directed these two localities to urgently complete the site handover in March 2025.

Thanhnien.vn

Source: https://thanhnien.vn/duong-ho-chi-minh-xuyen-rung-cao-su-o-binh-duong-thong-xe-ky-thuat-dip-304-185250222135955024.htm


Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product