The above information was confirmed by Mr. Le Huu Tuan - Deputy Head of Compensation and Site Clearance Board of Tan Binh District (HCMC) with VietNamNet reporter .

On January 10, Tan Binh district handed over the land with 34 houses located in alleys 111, 119, 166 and the frontage of Tran Van Du street to the investor to implement the project of connecting road Tran Quoc Hoan - Cong Hoa.

W-z6216249575344_0a06e0869accc1d01b6b7d8b48fb458a.jpg
6 houses on Tran Van Du street frontage have been demolished and handed over to the investor.
W-z6216249444074_8016fcbbff4d7879fb0c83e8bde3e76c.jpg
From Tran Van Du street, you can see the shape of the overpass on the route connecting Tran Quoc Hoan - Cong Hoa to Tan Son Nhat airport terminal T3. This bridge is 988m long, 17m wide with 4 lanes.
W-z6216249515130_a2af5949670b19927a29e7d9c93e0794.jpg
On December 27, 2024, Tan Binh District also handed over to the investor the premises of 12 houses, including 3 houses on Cong Hoa Street and 9 houses on C12 Street. In the photo is a row of 3 houses on Cong Hoa Street that have been demolished.

According to Mr. Tuan, the entire connecting road project has 85 affected cases, including 68 households and 17 units and organizations. The total land area recovered is more than 133,234m2.

"As of January 10, the project still has 22 houses stuck in the land, of which 6 households have received compensation and 1 household is being demolished. Tan Binh District is urgently mobilizing and propagating the remaining households to agree to soon hand over the land to the investor," Mr. Tuan informed.

W-z6216249481891_0f1b575d937a91060c12fe2e76bb5bd7.jpg
Within 10 days of receiving compensation, if households complete the handover of the site early, they will be rewarded by Tan Binh district with an amount of 15 million VND.
W-z6210852325014_a1aeb0bd5a5e97c22b6c25b6d7bb5418.jpg
Overall site clearance work as of January 10. There are still 16 households that have not agreed to the compensation plan. Graphics: Tan Binh District Site Clearance and Compensation Board.

On the investor side - the HCM City Traffic Construction Investment Management Board (Traffic Board) informed that the Tran Quoc Hoan - Cong Hoa connecting road project has basically completed the section from Phan Thuc Duyen tunnel to Hoang Hoa Tham street. 3 connection locations from the connecting road to T3 station including the elevated and underground roads are also ready for traffic connection.

The Traffic Department plans to open this section before Lunar New Year 2025 to reduce traffic pressure at Tan Son Nhat gateway.

The section from Hoang Hoa Tham Street to Cong Hoa - Truong Chinh is still stuck with the land acquisition of 22 households. Tan Binh District People's Committee plans to complete the land handover by February 20, so the entire route is expected to be completed and open to traffic by April 30.

W-z6211103599970_513850d2c6d62cefe56e0877dc77aa71.jpg

The middle section of the road connecting to the overpass in front of Terminal T3 of Tan Son Nhat Airport has completed the structure, installed railings and paved the bridge surface. The contractor mobilized machinery and workers to speed up the progress of rolling the ground and paving the road surface under the bridge to open to traffic on January 20.

W-z6216249515799_7a4262450867f4a4c98cda04be03e2f0.jpg
At the end of the more than 4,800 billion VND connecting road project, from Nguyen Duc Thuan to Cong Hoa street, about 700m long, has been basically completed but cannot be fully opened to traffic. The reason is that land acquisition problems have prevented many items from being constructed.
4,800 billion VND connecting tunnel at Tan Son Nhat gateway 1 day before opening to traffic

4,800 billion VND connecting tunnel at Tan Son Nhat gateway 1 day before opening to traffic

The construction package of the underpass of the Tran Quoc Hoan - Cong Hoa connecting road project is entering the "final" construction hours to open to traffic tomorrow, helping to relieve congestion right at the gateway to Tan Son Nhat airport.
The 4,800 billion VND connecting road to relieve traffic jams at Tan Son Nhat gateway is revealed

The 4,800 billion VND connecting road to relieve traffic jams at Tan Son Nhat gateway is revealed

The road connecting Tan Son Nhat gateway with a total investment of over VND4,800 billion to relieve traffic congestion has appeared with a 6-lane road surface being rolled and paved to meet the traffic opening schedule by the end of 2024.
4,800 billion VND road opens 700m more, reducing congestion at Tan Son Nhat gateway

4,800 billion VND road opens 700m more, reducing congestion at Tan Son Nhat gateway

The Tran Quoc Hoan - Cong Hoa connecting road project worth over 4,800 billion VND has just opened an additional 700m section, helping to reduce traffic congestion at Tan Son Nhat gateway in the area of ​​Thang Long street and Lang Cha Ca roundabout.