The Tran Quoc Hoan - Cong Hoa road project with a cost of more than 4,800 billion VND connecting Tan Son Nhat airport's T3 terminal still has 22 land issues.
The above information was confirmed by Mr. Le Huu Tuan - Deputy Head of Compensation and Site Clearance Board of Tan Binh District (HCMC) with VietNamNet reporter .
On January 10, Tan Binh district handed over the land with 34 houses located in alleys 111, 119, 166 and the frontage of Tran Van Du street to the investor to implement the project of connecting road Tran Quoc Hoan - Cong Hoa.
According to Mr. Tuan, the entire connecting road project has 85 affected cases, including 68 households and 17 units and organizations. The total land area recovered is more than 133,234m2.
"As of January 10, the project still has 22 houses stuck in the land, of which 6 households have received compensation and 1 household is being demolished. Tan Binh District is urgently mobilizing and propagating the remaining households to agree to soon hand over the land to the investor," Mr. Tuan informed.
On the investor side - the HCM City Traffic Construction Investment Management Board (Traffic Board) informed that the Tran Quoc Hoan - Cong Hoa connecting road project has basically completed the section from Phan Thuc Duyen tunnel to Hoang Hoa Tham street. 3 connection locations from the connecting road to T3 station including the elevated and underground roads are also ready for traffic connection.
The Traffic Department plans to open this section before Lunar New Year 2025 to reduce traffic pressure at Tan Son Nhat gateway.
The section from Hoang Hoa Tham Street to Cong Hoa - Truong Chinh is still stuck with the land acquisition of 22 households. Tan Binh District People's Committee plans to complete the land handover by February 20, so the entire route is expected to be completed and open to traffic by April 30.
The middle section of the road connecting to the overpass in front of Terminal T3 of Tan Son Nhat Airport has completed the structure, installed railings and paved the bridge surface. The contractor mobilized machinery and workers to speed up the progress of rolling the ground and paving the road surface under the bridge to open to traffic on January 20.
4,800 billion VND connecting tunnel at Tan Son Nhat gateway 1 day before opening to traffic
The 4,800 billion VND connecting road to relieve traffic jams at Tan Son Nhat gateway is revealed
4,800 billion VND road opens 700m more, reducing congestion at Tan Son Nhat gateway
Source: https://vietnamnet.vn/duong-hon-4-800-ty-dong-noi-san-bay-tan-son-nhat-con-vuong-22-mat-bang-2362171.html
Comment (0)