| Contractors are focusing on speeding up the construction progress of the roadbed. |
According to the report of the investor, the Provincial Management Board of Investment Projects for Construction of Traffic and Agricultural Works, taking advantage of favorable weather, they urged contractors to speed up the construction progress of the road.
Up to now, the roadbed construction progress has reached 22% of the volume; Song Rong bridge project has reached 28% of the volume. Other items such as drainage system, traffic safety... have reached about 12% of the volume. The disbursement result of the capital plan in 2025 has reached 90,003/107 billion VND, reaching 84.11%. The project construction completion milestone is before December 31, 2025.
The route connecting DT.265 from Dan Tien commune (Thai Nguyen) to Yen The (Bac Ninh) has a total length of 6.2km. The project investment objective is to strengthen traffic connection between Thai Nguyen province and Bac Ninh province, promote the circulation of goods, develop tourism, contribute to promoting socio -economic development, strengthen national defense and security, and gradually complete the traffic infrastructure system according to the plan.
Source: https://baothainguyen.vn/giao-thong/202510/giai-phong-mat-bang-tuyen-duong-ket-noi-dt265-tu-xa-dan-tien-di-yen-the-dat-977-4353d29/







Comment (0)