Coming to the construction site of Xuan Lai Kindergarten and the road leading to the school in mid-November, witnessing the bustling and urgent atmosphere of each group of workers, we can see the determination of the construction contractor in speeding up the progress of each project item. Mr. Tran Van Cuong, a technical officer of Ngoc Long Bac Ninh Limited Liability Company, said: "This year's rainy weather has greatly affected the progress of the project. However, right from the start of construction, the unit determined that this is a key project of the locality, related to the work of infrastructure restoration, serving the work of site clearance for Gia Binh International Airport, so we have focused on human resources, means, implemented many solutions, overcome difficulties, speed up progress, strive to complete and hand over the project according to plan."
![]() |
The road to Xuan Lai Kindergarten is being completed. |
The investment project to build Xuan Lai Kindergarten started in March 2025 and is scheduled to be completed on November 30, 2025. After more than 7 months of construction, with the great efforts and determination of the contractor, the progress of the basic packages basically meets the general goals of the entire project. Currently, the contractor has completed more than 90% of the total volume, the teams are focusing on completing (installing electrical and water equipment...) the classroom blocks, the administration building, the kitchen; implementing the construction of the outdoor infrastructure system; priming the project...
| The Xuan Lai Kindergarten project and the road leading to the school are invested by Gia Binh Construction Investment Project Management Board. The project is implemented on an area of 0.9 hectares, with a cost of nearly 70 billion VND, including the following items: Construction of new classrooms, administrative area (2 floors, 20 rooms); technical infrastructure system outside the house and auxiliary items. |
To meet the schedule, the unit is mobilizing 50 engineers and workers. The construction force focuses mainly on groups such as: Steel, formwork and masonry to strive to complete the foundation and columns of the school yard dome before November 20; complete the installation of equipment for classrooms, administration buildings, and the outside infrastructure before November 26.
For the road to the school, which was deployed from April 2025, it is planned to be completed by the end of December 2025. The road is more than 147 m long, 22.5 m wide (including sidewalks); synchronous technical infrastructure system (lighting, trees, drainage); total investment cost is more than 8.4 billion VND. At the starting point from National Highway 17 to the school, the construction unit has completed 70% of the work volume.
According to the construction site management department, although the progress of the items has been accelerated, the issue of quality and labor safety is always put first. On the first day of the week, the construction teams were informed and reminded to strictly follow the construction site's regulations on labor safety; measures for construction at height. The processes of checking input construction materials, quality control, ensuring the correct material standards before putting into construction.
The Xuan Lai Kindergarten project and the road to the school are invested by Gia Binh Construction Investment Project Management Board. The school construction project is implemented on an area of 0.9 hectares, with a cost of nearly 70 billion VND, including the following items: Construction of new classrooms, administrative area (2 floors, 20 rooms); technical infrastructure system outside the house and auxiliary items. According to the investor's assessment, up to now the project has basically met the schedule; ensured quality, labor safety and construction site hygiene. Mr. Nguyen Duc Thiem, Deputy Director of Gia Binh Construction Investment Project Management Board, affirmed: "To achieve the above large volume is a great effort of the investor and contractor because the implementation process encountered many difficulties. For example, the price of construction materials increased; the weather was rainy; and the construction road had to be built to the construction site". Despite the difficult construction conditions, the contractor has implemented many solutions such as: Pre-ordering and gathering construction equipment and materials to the construction site according to the construction plan of each item; hiring installation and pre-processing at the factory of construction-related components (schoolyard canopy, doors of all kinds, stair railings, etc.); adjusting working hours to limit the impact of weather.
In addition, during the construction process, the contractor regularly organizes to encourage teams and groups to strive to complete the work according to the set plan. The investor closely coordinates with the contractor through weekly and monthly meetings to promptly resolve any problems. Currently, there are no obstacles to the progress of completing Xuan Lai Kindergarten. Regarding the land clearance problem at the road project to the school, the relevant units are mobilizing people to hand over the land so that the contractor can synchronously deploy the road.
Along with urging contractors to quickly complete the project, the investor is also actively completing the documents to submit to the Department of Construction for acceptance and putting the project into use. From there, creating consensus among the people when implementing the infrastructure development investment policies of the province and the Central Government.
Source: https://baobacninhtv.vn/nguoi-dan-dong-thuan-cong-trinh-ve-dich-dung-hen-postid431206.bbg