Taking decisive action in land clearance and resettlement to ensure the progress of the Coastal Road Project.

On the morning of December 14th, Comrade Ta Anh Tuan, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, inspected the progress of the Provincial Coastal Road Project.

Báo Đắk LắkBáo Đắk Lắk14/12/2025

The delegation included leaders from relevant departments, agencies, and localities.

At the meeting, the Management Board of Investment and Construction Projects in the Eastern region of the province (the Management Board) reported in detail on the progress of the component projects, land clearance work, construction, and the situation of capital allocation and disbursement.

Comrade Ta Anh Tuan, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, directed the implementation of the Provincial Coastal Road Project.
Comrade Ta Anh Tuan, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, directed the implementation of the Provincial Coastal Road Project.

According to the report, the Provincial Coastal Road Project, implemented across multiple areas, plays a crucial role in connecting coastal transportation and promoting socio -economic development. During implementation, the project was divided into three independent investment phases to align with available funding.

To date, the construction project for the connecting section from Binh Kien ward to Tuy An Dong commune is progressing according to plan. Land handover has reached 6.732/14.67 km, equivalent to 46.09%. Son Hai Group Co., Ltd. – the construction contractor – is implementing various items such as organic soil excavation, weak soil treatment, road embankment excavation and filling, and concrete component production; the value of work completed has reached 32.5 billion VND.

The cumulative value of project implementation to date is over 129 billion VND. The total capital allocated to the project is 1,618 billion VND, and disbursement has reached nearly 738.9 billion VND.

The leaders of O Loan commune reported on the land clearance situation.
The leaders of O Loan commune reported on the land clearance situation to the Chairman of the Provincial People's Committee, Ta Anh Tuan.

For the construction project of the northern section of An Hai Bridge, the local authorities have handed over 4.8/7.48 km of the construction site, reaching 64%. The roadbed, drainage system, foundation, and surface paving are being implemented simultaneously.

The value of completed construction work reached VND 134 billion. The cumulative value of completed work is VND 183.2 billion. The total capital allocated to the project is VND 600 billion, and disbursements have reached VND 313.7 billion. The investor and contractors have developed a detailed schedule and are striving to complete the entire project in 2026.

Regarding the project to construct the connecting section between Xuan Dai Ward and Tuy An Dong Commune, the Management Board stated that the project is currently in the investment preparation phase. The investment policy proposal report has been submitted to the Department of Finance for appraisal through relevant submissions and documents. According to the plan, the project will be submitted, appraised, and approved in the first quarter of 2026, and the investment project will be approved in the second quarter of 2026 to proceed with the next steps.

The contractor is carrying out site leveling work in O Loan commune.
The contractor is carrying out site leveling work in O Loan commune.

During the inspection, leaders of Binh Kien ward and O Loan commune reported on the land clearance situation in the project area and the resettlement arrangements for affected households.

After conducting on-site inspections and listening to reports, Chairman of the Provincial People's Committee Ta Anh Tuan requested that localities and relevant units focus intensely on land clearance and resettlement, considering this a key task that determines the overall progress of the project.

Before January 31, 2026, Binh Kien ward must complete the resettlement plan and expedite land clearance for the two resettlement areas in the ward. Sections where land has been cleared must be promptly handed over to the contractor for construction. The An Phu resettlement area must be completed in the first quarter of 2026. Local authorities must proactively handle matters within their jurisdiction without waiting for instructions.

Regarding Tuy An Nam and O Loan communes, the Chairman of the Provincial People's Committee acknowledged the results achieved by the localities in land clearance for the construction route and resettlement areas.

Comrade Ta Anh Tuan requested that O Loan commune complete the land clearance for the Nhon Hoi resettlement area before December 31st, and strive to complete the land clearance for both resettlement areas in O Loan commune by May 2026, as a basis for accelerating land clearance and construction of related sections of the route.

Leaders of Tuy An Nam commune report on the progress of land clearance.
Leaders of Tuy An Nam commune report on the progress of land clearance.

For sections where land is already available, the Chairman of the Provincial People's Committee requested the contractor to accelerate progress, concentrate manpower and equipment for continuous construction, in order to generate the necessary volume for payment in December.

“The Management Board and relevant units will continue to focus on resolving difficulties, especially in land clearance, accelerating construction progress and capital disbursement, ensuring that the component projects of the provincial coastal road are implemented on schedule and meet the set objectives,” Chairman of the Provincial People's Committee Ta Anh Tuan emphasized.

Snow Fragrance

Source: https://baodaklak.vn/kinh-te/202512/quyet-liet-trong-giai-phong-mat-bang-tai-dinh-cu-de-bao-dam-tien-do-tuyen-duong-bo-ven-bien-7c306b2/


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Huynh Nhu makes history at the SEA Games: A record that will be very difficult to break.
The stunning church on Highway 51 lit up for Christmas, attracting the attention of everyone passing by.
The moment Nguyen Thi Oanh sprinted to the finish line, unrivaled in 5 SEA Games.
Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.

Same author

Heritage

Figure

Enterprise

Hanoi's churches are brilliantly lit, and the Christmas atmosphere fills the streets.

News

Political System

Destination

Product