Provincial Guest House Project, currently the construction volume is estimated at about 15% (construction package). The selection of contractors to supply and install equipment is underway. Chairman of the Provincial People's Committee Le Thanh Do assessed that the project progress basically meets the requirements and plans. However, the investor and the contractor at the end of the year, especially during the New Year and Lunar New Year, need to pay special attention to developing detailed and specific plans to ensure progress. Focus on human and material resources to construct 3 shifts and 4 teams; strengthen construction quality management; apply technology to the construction and completion process. During the construction process, if there are any difficulties or problems, the investor is required to promptly summarize and report to the province for resolution, in order to ensure the project is completed by March 31, 2024.

For packages 4 and 5 (Dien Bien Phu City) under the dynamic road project, the city has approved 14.61/31.8ha, reaching 45.95%, and the resettlement site has approved 1.25/3.2ha, reaching 39.0%. There are still some problems, such as: The work of determining land types and verifying land origins to serve as a basis for completing the land origin report is still very slow; the work of comparing cadastral maps in 1995, 1998, 2010, inventory books, documents through different periods, through the opinions of the community, reputable people can accurately determine the land use boundaries of households, owners of recovered land plots...

Chairman of the Provincial People's Committee Le Thanh Do requested the investor, Dien Bien Phu City People's Committee, relevant departments and branches to strengthen coordination to speed up progress, especially site clearance. Continue to mobilize cadastral officers of related communes and wards, if necessary, request the city to contract more people... to do site clearance for the project. Particularly for packages 4 and 5, it is necessary to focus on prioritizing the implementation of the section through the provincial administrative and political center; urgently resolve bottlenecks and areas where soil is taken to fill in order to coordinate soil for other packages. After the plan is approved, step up propaganda and mobilize people to make advance payments to hand over the site.

Inspecting the Dien Bien Airport Construction and Expansion Investment Project, Chairman of the Provincial People's Committee Le Thanh Do assessed that the project construction has been basically completed. The Chairman of the Provincial People's Committee requested to focus on ensuring fire prevention and fighting safety. To meet the schedule of putting Dien Bien Airport into operation from December 2, he requested relevant units and agencies to focus on industrial hygiene; requested the Department of Transport to coordinate with Vietnam Airports Corporation to plan to welcome the first flight after resuming operations.
Source
Comment (0)