On the evening of July 30, Ms. Y Lan, Chairwoman of the People's Committee of Bo Y Commune, Quang Ngai Province, said that the commune is coordinating to review the damage caused by water and waste overflowing from the Ngoc Hoi Solid Waste Treatment Complex, to have a plan to remove the problem and support the people.
“In addition, the commune is also making efforts to implement treatment measures to ensure the environment, helping people continue farming and aquaculture,” Ms. Y Lan added.

Ngoc Hoi Solid Waste Treatment Complex is located in Sa Loong commune, Quang Ngai province.
The project was approved for investment in 2017; construction, acceptance and operation from April 2025.
Currently, the project is managed, exploited and operated by the Project Management Board and Public Services of Bo Y Commune (belonging to Bo Y Commune).
Garbage collection and treatment project for 3 communes: Bo Y, Duc Nong and Sa Loong.

Initial information, on the same morning, a large hole appeared at the landfill of Ngoc Hoi Solid Waste Treatment Complex.
Thousands of cubic meters of water and waste remaining in the landfill were washed away, silting up the fish pond and affecting the surrounding environment.
Reporting on the incident, the Bo Y Commune Project Management and Public Service Board said that in recent days, due to the impact of prolonged heavy rain, a large amount of water accumulated in the landfill; high water pressure damaged the connection of the wastewater collection pipe of the system, causing water to overflow from the treatment system to the outside.
The large amount of water pushed some of the untreated waste out of the garbage storage area, affecting the ponds of surrounding households.

After the incident, the Project Management Board and the Commune Public Services quickly organized the collection and cleaning of all the waste that had spilled into the environment.
At the same time, reinforce the gabion to cover and isolate the incident area to minimize the spread of waste and water into the environment.
The Project Management Board and Commune Public Services have sent an official dispatch to the construction unit, requesting a plan to fix the broken pipe joint, ensuring that no more water and garbage will spill out.
According to Ms. Y Lan, initially, it was determined that about 11 households were affected by the above incident.
Source: https://www.sggp.org.vn/khu-xu-ly-rac-vua-van-hanh-da-hong-ong-nuoc-va-rac-thi-nhau-ra-ngoai-post806152.html