Khanh Hoa province leaders urge progress of "turtle" project

On October 28, Mr. Le Huyen, Vice Chairman of Khanh Hoa Provincial People's Committee, inspected the progress of the Le Thanh Ton Street renovation project (Nha Trang ward) which is under slow construction.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng28/10/2025

Khánh Hòa province leaders urge speed up the progress of the

dasua-970.jpg

Vice Chairman of Khanh Hoa Provincial People's Committee Le Huyen (pointing) inspects the Le Thanh Ton road renovation project. Photo: NHAT THANH

According to the report, the contractor has completed 97% of the technical trenches, sidewalk upgrades and renovations; over 97% of the drainage and wastewater systems; and 40% of the asphalt road surface. Currently, the unit is relocating the electrical, lighting, and telecommunications systems; and is committed to completing the entire project before November 10, 2025.

Vice Chairman of the Provincial People's Committee Le Huyen requested the Provincial Development Project Management Board to direct the contractor to organize construction day and night, ensuring progress and quality. The Nha Trang Ward People's Committee was tasked with imposing penalties if the construction unit continues to delay. During the construction process, the contractor must ensure traffic safety, urban aesthetics, address dangerous locations, and alleviate public concerns along the route.

Khanh Hoa Province Leaders Implement Practical Steps in Cow Washing Project.webp

The Le Thanh Ton street renovation project is now more than two months behind schedule. Photo: Hieu Giang

Previously, SGGP newspaper reported on the slow construction progress, scattered materials, and potential safety risks at this project. Several motorcyclists slipped and fell while passing through the unfinished sections, fortunately without sustaining any life-threatening injuries.

On September 8-9, the People's Committee of Nha Trang ward fined Khanh Anh Investment and Construction Joint Stock Company 12 million VND for carrying out construction on a road currently in use without placing warning signs and barriers as required; and demanded that the company rectify the situation and ensure safety throughout the construction process.

The project "Upgrading, renovating sidewalks and constructing new shared underground technical infrastructure on Le Thanh Ton Street" (referred to as the Le Thanh Ton Street beautification project) is approximately 1km long, located in the center of Nha Trang ward, and commenced in February 2025. The construction period is 180 days, with a contract completion date of August 20, 2025.

The project, originally managed by the Nha Trang City Construction Projects Management Board, has now been transferred to the Khanh Hoa Provincial Development Project Management Board with a total investment of over 30.4 billion VND.

HIEU GIANG

Source: https://www.sggp.org.vn/lanh-dao-tinh-khanh-hoa-thuc-tien-do-du-an-rua-bo-post820387.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

The moment Nguyen Thi Oanh sprinted to the finish line, unrivaled in 5 SEA Games.
Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.
The unforgettable beauty of shooting 'hot girl' Phi Thanh Thao at the SEA Games 33
Hanoi's churches are brilliantly lit, and the Christmas atmosphere fills the streets.

Same author

Heritage

Figure

Enterprise

Young people are enjoying taking photos and checking in at places where it looks like "snow is falling" in Ho Chi Minh City.

News

Political System

Destination

Product