On July 31, Rach Mieu 2 Bridge project will be completed.

On July 27, Mr. Tran Van Thi, Director of My Thuan Project Management Board, said that up to now, the overall progress of the Rach Mieu 2 Bridge Construction Investment Project (connecting Dong Thap and Vinh Long provinces) is 99% complete.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng27/07/2025

z6846056086078_2d832266472bade7e404f6ff9d2d36df.jpg
The road section of Rach Mieu 2 bridge project has completed asphalt concrete construction for about 13.7/14km.

According to Mr. Thi, the road has completed asphalt concrete construction for about 13.7/14km. The bridge section on the route has completed 5/5 bridges (Xoai Hot bridge, My Tho bridge, Tam Son bridge, Ba Lai bridge, Song Ma bridge).

z6846056037885_125a56b7c36a67738e649a042f191a31.jpg
The main bridge - Rach Mieu 2 bridge has completed the asphalt concrete pavement and basically completed the main construction items of the bridge.

The approach bridge and main bridge of Rach Mieu 2 Bridge have completed the asphalt concrete pavement and basically completed the main construction items of the bridge. Currently, the construction units are continuing to carry out the experimental work of measuring the vibration of the cables/shock absorbers, implementing the work of inspecting the bridge load test, etc.

On July 31, Rach Mieu 2 Bridge will be completed.

z6846056070543_d16a2eac173bbb7882524d6896e49ad1.jpg
z6846056018583_b32e47c29ec986511e3c3a420e0aab24.jpg
Construction units work day and night

It is expected that in early August, the units will meet to approve the project acceptance inspection council, then hand it over to Dong Thap and Vinh Long provinces.

z6846056072463_f76a1e6ed0f315b755591dd997daadc8.jpg
z6846056009760_b7cb0106e158a08d40cba571a1e3bbc3.jpg

The Rach Mieu 2 Bridge construction investment project is expected to be inaugurated and put into operation before September 2.

z6846056077782_280a3bd495e7589f6ef87b745774a37c.jpg

At the construction site, the units are continuing to maintain more than 35 construction teams; about more than 100 pieces of equipment; 350 workers and 70 technical staff... implementing construction in 3 shifts, 4 teams. All are determined to complete the project as directed by the Prime Minister .

z6846056056829_b8c6ab72528a160f8c829cdcb64730c1.jpg

The Rach Mieu 2 Bridge Project has its starting point at Dong Tam intersection (intersection between National Highway 1 and Provincial Road 870) in Dong Thap province; the project's end point is at about Km16+660 National Highway 60, about 0.71km from the northern abutment of Ham Luong Bridge, in Vinh Long province. The project has a total investment of more than 6,810 billion VND, with My Thuan Project Management Board as the investor.

z6846056032440_e6347a00472586f7e718a800faf8517f.jpg

Rach Mieu 2 main bridge is a cable-stayed bridge, with a length of 1,971.2m, a 4-lane level III delta road, the total length of the project is about 17.6km. When completed, the project will help reduce pressure on the existing Rach Mieu bridge, minimizing traffic congestion on weekends and holidays.

z6846056044085_29fea3d0d6adbf3b80b0041f9bf78d94.jpg
z6846056006926_43744ef0ebee630f645991ddd3d59993.jpg
On July 31, the entire Rach Mieu 2 bridge project will be completed.

Source: https://www.sggp.org.vn/ngay-31-7-cong-trinh-cau-rach-mieu-2-se-hoan-thanh-post805710.html


Comment (0)

No data
No data

Same tag

Same category

The peaceful golden season of Hoang Su Phi in the high mountains of Tay Con Linh
Village in Da Nang in top 50 most beautiful villages in the world 2025
Lantern craft village is flooded with orders during the Mid-Autumn Festival, making as soon as orders are placed.
Precariously swinging on the cliff, clinging to the rocks to scrape seaweed jam at Gia Lai beach

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product