Focus on site clearance, speed up disbursement of public investment capital

Chairman of Lam Dong Provincial People's Committee Ho Van Muoi requested the Department of Finance to take decisive action, coordinate with relevant units to monitor, adjust, and focus on disbursing public investment capital at the highest level.

Báo Lâm ĐồngBáo Lâm Đồng17/11/2025

On the morning of November 17, Deputy Secretary of the Provincial Party Committee and Chairman of the Lam Dong Provincial People's Committee Ho Van Muoi chaired a meeting to listen to the Department of Finance report on the disbursement of public investment capital in 2025 and discuss key solutions in the coming time. Also attending were Provincial Party Committee member and Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep.

h1.jpg
As of November 14, 2025, Lam Dong has disbursed 6,333 billion VND in public investment capital, reaching 33.88% of the plan.

According to the report of the Department of Finance, by November 14, 2025, Lam Dong had disbursed 6,333 billion VND, reaching 33.88% of the plan. The reasons for the delay include: Site clearance work at many projects has not reached an agreement with the people; Determining the origin of land, counting, appraising, and approving the site clearance plan is still limited; Some investors have not proactively managed, supervised, and urged contractors to implement; Contractor capacity is limited, lacking human resources and machinery, while investors have not resolutely handled responsibilities.

h8.jpg
Director of the Department of Finance Ton Thien San explains the reason for slow capital disbursement

“Many contractors are incompetent and do not arrange enough personnel and machinery according to the bidding documents. Meanwhile, investors are not really determined in handling responsibilities,” emphasized Director of the Department of Finance Ton Thien San.

h7.jpg
Deputy Director of the Department of Finance Tran Dinh Ninh proposed many solutions to speed up the disbursement of public investment capital in Lam Dong.

At the meeting, the Department of Finance proposed many important contents to promote the disbursement of public investment capital. Investors need to identify the unit assigned with investment capital to implement the project, thereby taking full responsibility before the Chairman of the Provincial People's Committee if the disbursement fails.

h2(1).jpg
Leaders of Lam Dong Department of Finance at the meeting

Investors step up coordination with local authorities to ensure site clearance progress. Based on the signed contract, investors compare the construction site and actual volume to take measures to handle contractors' delays.

h6.jpg
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep emphasized that the Department of Finance is proactive and flexible in transferring capital sources.

Regarding the promotion of public investment disbursement, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep emphasized that the task of capital disbursement is currently very heavy. The Department of Finance reviews capital sources that cannot be disbursed in 2025, especially central capital, to propose immediate return to the central government. At the same time, the Department focuses on urging investors and construction units to speed up project progress, advise and issue detailed lists and projects for national target programs to promote disbursement at the end of the year.

h3(1).jpg
Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Ho Van Muoi emphasized that localities and investors are determined in site clearance work.

Concluding the meeting, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee Ho Van Muoi emphasized that in the field of public investment alone, the provincial leaders have given very strong direction. In the past 2 months, the entire political system has taken serious and high-level action, however, the capital disbursement results have not yet met expectations.

There is no other way to disburse public investment capital than to continue to be determined. By the end of 2025, Lam Dong must strive to disburse above the national average. In the immediate future, site clearance is still the most important step.

Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Ho Van Muoi

h4(1).jpg
Leaders of departments and branches attended the meeting

“The Department of Finance shall coordinate with the Provincial People's Committee Office to advise and issue a telegram immediately to units and localities to take drastic action on the issue of site clearance. During the implementation process, if any difficulties arise, the facility must immediately report to the Provincial People's Committee. Units and localities shall concentrate their professional forces to perform well the assigned functions and tasks,” Chairman of the Provincial People's Committee Ho Van Muoi directed.

The specialized departments of the Department of Finance coordinate with relevant units, unite and support each other in disbursing public investment capital, striving to achieve the best results.

Source: https://baolamdong.vn/tap-trung-giai-phong-mat-bang-day-nhanh-tien-do-giai-ngan-von-dau-tu-cong-403351.html


Comment (0)

No data
No data

Same tag

Same category

Buckwheat flower season, Ha Giang - Tuyen Quang becomes an attractive check-in spot
Watching the sunrise on Co To Island
Wandering among the clouds of Dalat
The blooming reed fields in Da Nang attract locals and tourists.

Same author

Heritage

Figure

Enterprise

Vietnamese model Huynh Tu Anh is sought after by international fashion houses after the Chanel show.

News

Political System

Destination

Product