Adverse weather slows down construction progress of upgrading two roads in the Mekong Delta region

Báo Xây dựngBáo Xây dựng17/12/2024

As of the first week of December 2024, the construction progress of the two projects Cao Lanh - Lo Te and Lo Te - Rach Soi has not met the plan due to unfavorable weather conditions.


Regarding the implementation status of the two projects Cao Lanh - Lo Te and Lo Te - Rach Soi, the Department of Construction Investment Management ( Ministry of Transport ) said that after about 6 months of construction, up to the first week of December 2024, the project's construction output reached 11% of the contract value, 7% slower than planned.

Thời tiết bất lợi làm chậm tiến độ thi công nâng cấp hai tuyến đường bộ khu vực ĐBSCL- Ảnh 1.

Construction of upgrading Lo Te - Rach Soi route (Photo: Huong Ngan)

The period from the start of construction to November 2024, which is the rainy season, makes it difficult to scrape, recycle, and reinforce the asphalt concrete road surface, which is an objective reason given.

"Subjectively, the project is behind schedule because contractors have not focused resources on construction implementation and have not mobilized enough human resources, machinery and equipment according to the required schedule.

By the end of November 2024, the contractor has mobilized: 3/5 recycling scraping lines, 2/5 asphalt concrete paving lines, 5/8 soil cement pile drilling rigs, 3/8 construction points for the transition slab at the head of the box culvert, 3/4 construction points for expanding the emergency lane, especially Hai Dang Joint Stock Company and the special subcontractor 469 Joint Stock Company", the Department of Construction Investment Management informed.

The implementation time falls right in the rainy season, which is also the reason why the Lo Te - Rach Soi project has not met the schedule.

As of the first week of December, the project's construction output reached 14% of the contract value, about 5% behind schedule.

In addition, the sand from the new mine introduced by Dong Thap Provincial People's Committee will only be exploited from December 2024; the area of ​​Lo Te intersection is expected to be handed over by the locality in January 2025, which also greatly affects the progress at the construction site.

The Cao Lanh - Lo Te project is 29km long. The investment scope includes asphalt concrete paving the main road surface and constructing a system of service roads along the route, arranging a fence system and completing the traffic safety system in compliance with the National Technical Regulations on road signs.

The Lo Te - Rach Soi project is over 51km long. Within the scope of investment and upgrading, the project only needs to lay asphalt concrete to strengthen the road surface and reorganize traffic, without having to clear the land.



Source: https://www.baogiaothong.vn/thoi-tiet-bat-loi-lam-cham-tien-do-thi-cong-nang-cap-hai-tuyen-duong-bo-khu-vuc-dbscl-192241217192655605.htm

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Notre Dame Cathedral in Ho Chi Minh City is brightly lit to welcome Christmas 2025
Hanoi girls "dress up" beautifully for Christmas season
Brightened after the storm and flood, the Tet chrysanthemum village in Gia Lai hopes there will be no power outages to save the plants.
The capital of yellow apricot in the Central region suffered heavy losses after double natural disasters

Same author

Heritage

Figure

Enterprise

Pho 'flying' 100,000 VND/bowl causes controversy, still crowded with customers

News

Political System

Destination

Product