TPO - With the goal of reducing traffic congestion at the Giai Phong - Kim Dong intersection, in October 2022, the Hanoi city government commenced the construction of an underpass project with a total investment of over 700 billion VND across Giai Phong road. After more than two years of construction, the area enclosed by the road barriers has now been expanded to allow for the construction of the open tunnel sections.
TPO - With the goal of reducing traffic congestion at the Giai Phong - Kim Dong intersection, in October 2022, the Hanoi city government commenced the construction of an underpass project with a total investment of over 700 billion VND across Giai Phong road. After more than two years of construction, the area enclosed by the road barriers has now been expanded to allow for the construction of the open tunnel sections.
VIDEO : Construction site and current traffic conditions through the Ring Road 2.5 underpass construction site. |
Current status of construction of the underpass across Giai Phong Street on October 30th. |
After excavating and constructing some sections of the enclosed underground tunnel, the fenced-off area has now been expanded on Giai Phong and Kim Dong streets to construct the open tunnel sections. This has caused difficulties for commuters and traffic congestion frequently occurs during peak hours at the Giai Phong - Kim Dong intersection. |
The central area of the Giai Phong - Kim Dong intersection is currently being fenced off for the construction of a deep pit leading down to the underpass. |
According to a representative of the main contractor, CIENCO 4 Corporation, several tunnel sections on the Dinh Cong side of the underpass have been completed, and the retaining wall has been finished. |
The access roads to and from the tunnel on the Dinh Cong side are also basically completed. |
According to the main contractor, the construction units are currently focusing on building the open and closed tunnel sections along the Giai Phong - Kim Dong road. |
Construction site for the Ring Road 2.5 underpass on the Giải Phóng and Kim Đồng streets side. |
The tunnel under the Ring Road 2.5 at the Giai Phong intersection has taken shape after more than two years of construction. The project is expected to be completed in 2025. |
On October 6, 2022, the Hanoi People's Committee officially commenced construction of the underground tunnel for Ring Road 2.5, passing through the Giai Phong - Kim Dong intersection.
The project has a total investment of over 770 billion VND; the tunnel is 460 meters long, with 4 lanes for motor vehicles, aiming to reduce traffic congestion at the existing intersection and complete the Ring Road 2.5. The project construction period is from 2022 to 2025.
To carry out the project, the investor, the Hanoi Traffic Construction Investment Project Management Board, and the contractors have recently coordinated with competent authorities to barricade two-thirds of Giai Phong Street and Kim Dong Street, and prohibit many types of vehicles from passing through to implement the project.
Source: https://tienphong.vn/ham-chui-qua-duong-giai-phong-ra-sao-sau-2-nam-thi-cong-post1686955.tpo






Comment (0)