Vietnam.vn - Nền tảng quảng bá Việt Nam

The shape of Dai Ngai 1 bridge connecting Can Tho and Vinh Long after 1 year of construction

Dai Ngai 1 Bridge across the Hau River, connecting Can Tho and Vinh Long, is gradually taking shape after 1 year of construction.

Báo Thanh niênBáo Thanh niên05/11/2025

On November 5, news from Project Management Board 85 - Ministry of Construction said that the Dai Ngai bridge project and the two approach roads are divided into two packages: package 11-XL (Dai Ngai 2 bridge) has been completed, the road is in the process of unloading crushed stone construction and preparing to construct the asphalt concrete layer; package 15-XL (Dai Ngai 1 bridge) ensures progress.

- Photo 1.

Dai Ngai 1 Bridge connecting Vinh Long and Can Tho City is gradually taking shape.

PHOTO: NAM LONG

Accordingly, there are currently 44 construction teams at the construction site. Of which, Dai Ngai 1 Bridge has 26 construction teams (10 bored pile construction teams, 12 pier construction teams and 4 line construction teams) with a total of 43 technical staff, 296 workers and 120 machines and equipment.

- Photo 2.

Dai Ngai 1 bridge pier is under construction on the bank of Can Tho city.

PHOTO: NAM LONG

- Photo 3.

Construction workers on site

PHOTO: NAM LONG

Specifically, roadbed excavation: 10,725/10,725 m 3 , reaching 100%; weak soil treatment, wick placement: 0.6/0.6 km, reaching 100%; soil cement piles: 0.16/0.16 km, reaching 100%; K95 foundation filling 24,650/69,348 m 3 , reaching 35.54%; bridge project 1/1 bridge under construction reaching 100% (construction of 32,887/36,416 m bored piles, reaching 90%; pouring concrete for 23/48 abutments and piers, reaching 48%; casting 102/294 girder slabs, reaching 35%).

- Photo 4.

Roadbed construction unit on Vinh Long side

PHOTO: NAM LONG

- Photo 5.

The piers of Dai Ngai 1 bridge are gradually taking shape.

PHOTO: NAM LONG

Dai Ngai 2 Bridge alone currently has 6 roadbed construction sites, 7 cross-culvert construction sites and 4 embankment reinforcement sites for Tran De channel.

Specifically, roadbed excavation: 87,628/97,935 m 3 , reaching 89%; weak soil treatment reaching 100%; K95 embankment: 629,915/701,658 m 3 , reaching 90%; K98 embankment: 10,175/52,252 m 3 , reaching 19%; asphalt concrete: 27,294/343,891 m 2 , reaching 8%; drainage culverts of all kinds: 13/43 culverts, reaching 30%; 6/6 bridges under construction reaching 100%.

- Photo 6.

Workers actively work the 3rd shift on the construction site.

PHOTO: NAM LONG

- Photo 7.

Dai Ngai 1 Bridge is the second largest cable-stayed bridge in Vietnam.

PHOTO: NAM LONG

- Photo 8.

Roadbed construction at night on Vinh Long bank

PHOTO: NAM LONG

- Photo 9.

The bridge piers on the Can Tho City side are gradually being completed.

PHOTO: NAM LONG

According to Project Management Board 85, the Dai Ngai 2 Bridge project is being implemented to ensure quality, labor safety and environmental sanitation. The bridge construction progress exceeds the approved schedule, but the road progress is behind schedule. Asphalt concrete is expected to be laid this December.

Dai Ngai 1 Bridge is under construction, ensuring quality, labor safety and environmental sanitation, and construction progress basically meets requirements.

The Dai Ngai Bridge project has a total investment of nearly 8,000 billion VND. The total length of the route is about 15.14 km. The starting point intersects with National Highway 54, in Tieu Can Commune, Vinh Long (formerly Hung Hoa Commune, Tieu Can District, Tra Vinh). The end point intersects with Nam Song Hau National Highway, Cu Lao Dung Commune, Can Tho City (formerly Long Duc Commune, Long Phu District, Soc Trang).

The project includes two main bridges, Dai Ngai 1 Bridge and Dai Ngai 2 Bridge, invested by Project Management Board 85. This is the third cable-stayed bridge across the Hau River, after Can Tho Bridge and Vam Cong Bridge.

Source: https://thanhnien.vn/hinh-hai-cau-dai-ngai-1-noi-can-tho-va-vinh-long-sau-1-nam-khoi-cong-18525110509070135.htm


Comment (0)

No data
No data

Same tag

Same category

Hero of Labor Thai Huong was directly awarded the Friendship Medal by Russian President Vladimir Putin at the Kremlin.
Lost in the fairy moss forest on the way to conquer Phu Sa Phin
This morning, Quy Nhon beach town is 'dreamy' in the mist
Captivating beauty of Sa Pa in 'cloud hunting' season

Same author

Heritage

Figure

Enterprise

Ho Chi Minh City attracts investment from FDI enterprises in new opportunities

News

Political System

Destination

Product