The Hau Loc 2 110kV transmission line and substation project has been completed and energized.

On December 11, 2025, Thanh Hoa Power Company completed the acceptance testing and commissioning of the Hau Loc 2 110kV transmission line and substation.

Báo Thanh HóaBáo Thanh Hóa12/12/2025

Accordingly, this project includes a 15.97 km long, double-circuit 110kV power line with 64 pole locations, using ACSR 300/39 conductors; connecting from the 220kV Bim Son - 110kV Nga Son power line at pole 65 to the 110kV Hau Loc 2 substation.

The Hau Loc 2 110kV transmission line and substation project has been completed and energized.

Inspection and acceptance testing before energizing the Hau Loc 2 110kV power line and substation.

The Hau Loc 2 110kV substation is designed with a capacity of 2×40 MVA. Phase 1 involves the installation of a 40 MVA transformer, internally transferred; synchronizing the 110kV equipment system, line bays, transformer bays, busbars, and 35kV and 22kV medium-voltage switchgear. The substation's technical infrastructure meets the requirements for long-term expansion, enhanced connectivity, and reliable operation of the regional power grid.

The Hau Loc 2 110kV transmission line and substation project has been completed and energized.

Workers from the Thanh Hoa High-Voltage Grid Operation and Management Team are completing the final steps in the installation of equipment at the Hau Loc 2 110kV substation before energizing it.

Once operational, the project will ensure a stable power supply for the communes of Hau Loc, Trieu Loc, Dong Thanh, Hoa Loc, and Van Loc; meet the high power demand of the Lien Hoa Industrial Cluster (38 hectares, expected to require approximately 30 MVA in 2027) and the Hoa Loc Industrial Cluster; and simultaneously eliminate intermediate substations, completing the medium-voltage loop with the Hoang Hoa, Ha Trung, Nga Son, and Hau Loc substations.

Completing the energization in the last month of 2025 is of particular importance, enhancing the power supply capacity for the region, reducing the load on existing substations, and ensuring stable power supply during the Lunar New Year of the Horse 2026.

The Hau Loc 2 110kV transmission line and substation project has been completed and energized.

Mr. Hoang Duc Hau - Deputy Director of Thanh Hoa Power Company (standing in the middle) poses for a commemorative photo with representatives of the construction contractor and company staff and employees on the occasion of the completion of the acceptance and energization of the Hau Loc 2 110kV transmission line and substation.

Mr. Hoang Duc Hau, Deputy Director of Thanh Hoa Power Company, stated: "The Hau Loc 2 110kV power line and substation is a key project in the development of the province's medium and high voltage power grid. The completion of this project is the result of tremendous efforts from the construction units and the active support of the local government and people. This will be an important foundation for ensuring a safe and continuous electricity supply to serve socio -economic development and the daily needs of the people in the coming period."

Hung Manh

Source: https://baothanhhoa.vn/hoan-thanh-dong-dien-cong-trinh-duong-day-va-tba-110kv-hau-loc-2-271545.htm


Comment (0)

Please leave a comment to share your feelings!

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product