A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction.

Báo Tiền PhongBáo Tiền Phong04/03/2024


TPO - After more than a year of construction, taking advantage of even long holidays to accelerate the project's progress, the underpass for motor vehicles on Ring Road 2.5, passing through the Giai Phong - Kim Dong intersection, has now taken shape.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 1).

After completing land clearance, over the past year the project implementing units have begun construction of both open and closed tunnel sections. In Dinh Cong ward, the tunnel has already taken shape.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 2).

On the Định Công side, construction units have completed 9 open tunnel sections and 1 closed tunnel section (the part of the tunnel that runs underground under the railway and Giải Phóng road).

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 3).

After the tunnel sections and retaining walls are completed, the tunnel's cross-sectional width on each side is 2 lanes for mixed traffic.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 4).

At the project site on the morning of February 27th, Mr. Do Duc Hung, representative of the investor, the Hanoi Traffic Construction Investment Project Management Board, stated that after completing the pouring of 9 open tunnel sections and 1 closed tunnel section on the Dinh Cong side, the contractors are currently constructing drainage ditches along both sides.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 5).

Regarding the current construction status of the project in Dinh Cong ward, Mr. Ho Duc Phuc (Cienco4 Corporation - the main contractor) stated that the tunnel construction in Dinh Cong ward is basically complete. However, the project cannot proceed with the access road to the tunnel because one household has erected a temporary shack and is encroaching on the land (photo 1), and a 630 KVA electrical transformer station is also obstructing the construction (photo 2).

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 6).

Regarding the project on Kim Dong Street (Giap Bat Ward, Hoang Mai District), the site is being expanded to construct an underpass over Giai Phong Street, an open tunnel, and access roads...

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 7).

The site at the Giai Phong - Kim Dong intersection is currently being widened by the construction unit by installing a median strip.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 8).

After the intersection expansion is completed, all vehicles traveling on Giai Phong Street will use the temporary road towards the newly expanded Kim Dong Street, and the intersection area will be fenced off for drilling and excavation of the main tunnel.

A firsthand look at the 2.5 Ring Road via Giai Phong-Kim Dong after more than a year of construction (photo 9).

It is expected that starting in May 2024, the drilling and excavation of the tunnel under Giai Phong Street to connect Ring Road 2.5 to Kim Dong Street will be carried out by the construction units.

The Ring Road 2.5 underpass project across Giai Phong Street has a total length of 460 meters, with 4 lanes for motor vehicles and runs underground through the Giai Phong - Kim Dong intersection. The project commenced on October 6, 2022, with an investment of 778 billion VND, and is scheduled for completion in the first quarter of 2025. Its goal is to complete the Ring Road 2.5 route and reduce traffic congestion at the Giai Phong - Kim Dong intersection.

At the project site on February 27th, Mr. Do Duc Hung, from Supervision Department 5, Hanoi City Investment and Construction Project Management Board for Transportation Projects (the investor), stated that the project is being constructed day by day and is still on track to open to traffic in the second quarter of 2025.

Party



Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product