NTO - Summary of progress of the Coastal Cities Sustainable Environment Project - Phan Rang City Sub-project

Việt NamViệt Nam27/09/2023

On September 27th, Mr. Le Huyen, Vice Chairman of the Provincial People's Committee, chaired a meeting with the World Bank (WB) delegation to summarize the progress of the Sustainable Environment Project for Coastal Cities - Phan Rang - Thap Cham City Sub-project.

The Phan Rang - Thap Cham City sub-project commenced in June 2016 and is expected to be completed on June 30, 2024. According to the Provincial Water Sector ODA Project Implementation and Capacity Building Board (the investor), the cumulative disbursement of ODA and counterpart funds from the beginning of the project to date has reached 65%. Four out of four construction packages in phase 1 have been completed, and efforts are currently focused on implementing nine construction packages in phase 2. The project affects a total of 1,584 households, with 15 households yet to hand over their land.

Comrade Le Huyen, Vice Chairman of the Provincial People's Committee, chaired the meeting.

After listening to the project management board's progress report and conducting on-site monitoring, the WB delegation members noted significant progress in the construction of various components, with some projects completed, bringing joy to the people in the beneficiary areas. They also recommended that the province further strengthen the disbursement of funds, develop a plan to definitively resolve outstanding issues; expedite the construction of the Tan Tai Canal, Cha La Canal, and Dong Hai Lake; ensure labor safety during construction, maintain environmental hygiene on the construction site to avoid impacting the lives and activities of the people, and expedite the connection of wastewater to the common drainage system.

Speaking at the meeting, the Vice Chairman of the Provincial People's Committee thanked the World Bank delegation for their continuous support in implementing the project. Based on the delegation's proposals and recommendations, the province will focus on directing the investor, relevant departments, and localities to enhance coordination, proactively review all remaining tasks, especially urgently completing land clearance, preparing detailed construction schedules for items where land is available, and allocating counterpart funds to ensure the project is completed as committed to the World Bank.


Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product