Quang Tri: Some basic infrastructure projects are still stuck in site clearance.

Up to now, 3/7 projects under the Basic Infrastructure Project for Comprehensive Development of Nghe An, Ha Tinh, Quang Tri Provinces (BIIG2 Project) - Sub-project of Quang Binh Province (old) still have problems with compensation and site clearance that have existed for many years.

Báo Đầu tưBáo Đầu tư29/12/2024

On the afternoon of July 17, Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu inspected the site clearance and resettlement work and held a meeting to review the progress of the projects under the Basic Infrastructure Project for Comprehensive Development of Nghe An, Ha Tinh, Quang Tri Provinces (BIIG2 Project) - Sub-project of Quang Binh Province (old).

Accordingly, Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu inspected 3 projects: Dinh Muoi tourist route, the road connecting National Highway 1 bypass with the East branch of Ho Chi Minh road, the road from Loc Ninh commune (old) to Dong Hoi Northwest Industrial Park.

Vice Chairman of the Provincial People's Committee directly inspected the progress of the project of the Road connecting from the National Highway 1 bypass to the East branch of Ho Chi Minh Road.
Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu (front row, 3rd from right in photo) inspects the progress of the project of the connecting road from National Highway 1 bypass to the East branch of Ho Chi Minh road.

For the Dinh Muoi tourist route project, the Quang Ninh Project Management Board (PMU) for Investment, Construction and Land Fund Development (PLDD & PTQD) is in charge of site clearance.

According to the report of the Project Management Board, the project has a total affected area of 16.77 hectares of 20 households and 3 organizations; to date, compensation and site clearance work has been completed with a total area of 16.60/16.77 hectares, reaching 98.99% of 13 households and 3 organizations. Currently, there are 7 households with garden land adjacent to residential land and residential land with a total area of 0.17 hectares that have not completed site clearance and resettlement land allocation.

For the road project connecting Highway 1 bypass with the East branch of Ho Chi Minh road, the Dong Hoi Construction Investment and Development Project Management Board is in charge of site clearance and compensation. This project has a total affected area of 5.88 hectares that must be recovered from 82 households and 3 organizations.

According to the project management board, the project has completed site clearance with a total area of 5.63/5.88 ha, reaching 95.74% of 78 households and 3 organizations. Currently, the project scope is still stuck with incomplete compensation and site clearance for 4 households and 1 organization with a total area of 0.25 ha.

For the road project from Loc Ninh commune (old) to Dong Hoi Northwest Industrial Park, the Dong Hoi Construction Investment and Development Project Management Board is in charge of site clearance and compensation. The project has a total affected area of 11.94 hectares, including 240 households and 3 organizations. Up to now, the Project Management Board has completed site clearance and compensation with a total area of 11.13/11.94 hectares, reaching 93.22% of 210 households and 3 organizations. Currently, there are 30 households with residential land and garden land adjacent to residential land with a total area of 0.81 hectares that have not yet completed compensation and site clearance.

After directly inspecting the progress of the projects, Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu had a working session with relevant departments, branches, units and localities.

Mr. Nguyen Viet Vuong, Director of BIIG2 Project Management Board - Department of Finance reported on the progress of ongoing projects.
Mr. Nguyen Viet Vuong, Director of BIIG2 Project Management Board - Quang Tri Department of Finance reported on the progress of ongoing projects.

At the meeting, Mr. Nguyen Viet Vuong, Director of BIIG2 Project Management Board - Quang Tri Department of Finance, said that the Department is currently implementing the BIIG2 Project with a loan from the Asian Development Bank (ADB). The project consists of 7 component sub-projects with an implementation period until September 30, 2025.

In recent times, the Quang Tri Department of Finance, together with other departments, sectors and localities, has actively handled and resolved many issues related to compensation and site clearance, and has basically completed a number of projects to ensure progress. However, 3/7 projects still have problems with compensation and site clearance that have existed for many years, greatly affecting the progress of implementation.

At the meeting, representatives of leaders of departments, branches and localities proposed a number of opinions and recommendations on compensation, support, site clearance for projects; planning adjustment, land use conversion, resettlement arrangement; measures to implement resettlement areas, land allocation for resettlement to households... to speed up the implementation of BIIG2 Project.

Speaking at the meeting, Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu requested that in the coming time, units and localities continue to mobilize to raise people's awareness of the meaning and importance of the project. If there are complicated and prolonged complaints, a plan must be developed to protect the construction.

Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu gave a speech at the meeting.
Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu gave a speech at the meeting.

In addition, Vice Chairman Phan Phong Phu requested departments, branches and localities to proactively deploy plans to implement works and projects in the direction of "Clear people, clear work and clear responsibilities"; consider and handle recommendations from households related to planning adjustments, land use conversion, resettlement arrangements; for investors in resettlement areas, speed up the progress of resettlement areas and allocate resettlement land to each household.

Vice Chairman of Quang Tri Provincial People's Committee Phan Phong Phu also assigned the responsibility to the Provincial People's Committee Office to urge and monitor the progress of projects and promptly report to the Provincial People's Committee for consideration and resolution.

Source: https://baodautu.vn/quang-tri-mot-so-du-an-ha-tang-co-ban-con-vuong-giai-phong-mat-bang-d334267.html


Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product