Vietnam.vn - Nền tảng quảng bá Việt Nam

Focus on removing land clearance problems and speeding up project implementation progress.

On the afternoon of November 17, comrade Bui Van Luong, member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee, chaired a working session with departments, branches and units to review the progress of the project of the connecting road from Bac Son road to the Thai Nguyen province sports complex; the project of investing in construction and business of infrastructure of Phu Binh Industrial Park.

Báo Thái NguyênBáo Thái Nguyên17/11/2025

Comrade Bui Van Luong, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee chaired the meeting.
Vice Chairman of the Provincial People's Committee Bui Van Luong chaired the meeting.

The route connecting Bac Son Street to Thai Nguyen Provincial Sports Complex is 2.71km long. The starting point connects with the section from Km0+00 (intersection with Bac Son Street) to Km0+139.18 in the residential area of ​​Bac Son Street extension; the end point connects with Thai Nguyen Stadium Road.

The project has a planned scale including: 36m wide roadbed, 21m road surface, 12m sidewalk and 3m median strip, synchronous investment in bridges, drainage and technical infrastructure. The project is constructed by Corporation 319 - Ministry of National Defense , started on December 30, 2024, expected to be completed on September 26, 2025, but the construction unit has requested an extension to December 31, 2025.

Sectors and units report on the progress of the project of the connecting road from Bac Son road to the sports complex of Thai Nguyen province.
Sectors and units report on the progress of the project of the connecting route from Bac Son road to the sports complex of Thai Nguyen province.

The main reasons for the delay are unfavorable weather and site clearance issues. Specifically: The total area that needs to be cleared is 11.9 hectares, and by September 10, 2025, 11.63 hectares had been handed over, reaching 97.7%, and all 18/18 graves had been relocated. There are still some households that have not agreed with the draft compensation plan.

Speaking at the meeting, Mr. Bui Van Luong acknowledged the efforts of the units but emphasized that the progress was still slow, in which site clearance was the decisive step and the biggest bottleneck. The Vice Chairman of the Provincial People's Committee requested Dai Phuc commune and the Land Fund Development Center of Region I to speed up the completion of the remaining area and the arising locations before November 19, ensuring full procedures, and at the same time, strengthening propaganda and dialogue to create consensus among the people.

For cases of intentional non-compliance, the Vice Chairman of the Provincial People's Committee requested enforcement and handover of the site to the contractor before November 21. Electricity, water and technical infrastructure suppliers must closely coordinate with the investor to carry out relocation and adjustment to avoid new problems.

The Vice Chairman of the Provincial People's Committee assigned the Project Management Board for Investment in Construction of Traffic and Agricultural Works to urge contractors to take advantage of the weather, mobilize maximum machinery, human resources, and work overtime to speed up construction; complete the entire route before November 25, strive to open the route before November 30, meeting the local political tasks.

Representative of Kinh Bac Urban Development Corporation - JSC spoke at the meeting.
Representative of Kinh Bac Urban Development Corporation - JSC spoke at the meeting.

For the Phu Binh Industrial Park Infrastructure Investment and Business Project, the investor is Kinh Bac Urban Development Corporation - JSC. The total planned area of ​​the Project is 675 hectares (phase 1 covers 190 hectares, in 3 communes: Phu Binh, Kha Son and Tan Thanh). The number of households affected in phase 1 is about 1,250, of which 600 households must relocate. Currently, the total implemented area is 31.94 hectares; the number of affected households is 355; of which 24 households must relocate.

Local representatives exchanged at the meeting.
Local representatives exchanged at the meeting.

The three communes of Phu Binh, Kha Son and Tan Thanh have organized declaration and counting; made payment and provisional compensation; at the same time, are publicizing the second phase of compensation and resettlement support plan and continuing to complete the dossiers for the remaining households.

Based on the opinions at the meeting, the Vice Chairman of the Provincial People's Committee requested the Provincial Land Fund Development Center to coordinate with departments, branches and localities to complete documents and procedures to pay compensation to people; at the same time, localities must propagate, remove obstacles, and ensure full compliance with regulations on resettlement.

Vice Chairman of the Provincial People's Committee Bui Van Luong delivered a concluding speech at the meeting.
Vice Chairman of the Provincial People's Committee Bui Van Luong delivered a concluding speech at the meeting.

The Vice Chairman of the Provincial People's Committee requested the investor to urgently complete the process so that localities can issue procedures related to land allocation, as a basis for construction implementation. To ensure the progress of starting construction of the planned area, the investor must complete the dossier to submit to the Department of Agriculture and Environment for the land funds within the project scope, and at the same time send the Department of Construction a temporary connection plan to serve the start of construction and accompanying technical procedures.

Along with that, the investor coordinates with departments and branches to determine the infrastructure, electricity and water conditions for construction. Specialized departments and branches are responsible for urging, appraising documents, assessing environmental impacts, and at the same time coordinating to remove difficulties and create favorable conditions for the project to be implemented on schedule.

Source: https://baothainguyen.vn/giao-thong/202511/tap-trung-thao-go-vuong-mac-mat-bang-day-nhanh-tien-do-trien-khai-cac-du-an-08d0837/


Comment (0)

No data
No data

Same tag

Same category

Buckwheat flower season, Ha Giang - Tuyen Quang becomes an attractive check-in spot
Watching the sunrise on Co To Island
Wandering among the clouds of Dalat
The blooming reed fields in Da Nang attract locals and tourists.

Same author

Heritage

Figure

Enterprise

Vietnamese model Huynh Tu Anh is sought after by international fashion houses after the Chanel show.

News

Political System

Destination

Product