Statistics of land clearance in Lao Cai station area

After receiving the land clearance dossier, the Lao Cai - Coc San Regional Project Management Board organized a census and counting of households in the affected area of ​​Component Project 1: Investing in infrastructure connecting stations on the route and station squares under the Lao Cai - Hanoi - Hai Phong Railway Construction Investment Project.

Báo Lào CaiBáo Lào Cai17/11/2025

baolaocai-br_galaocai-1.jpg
Land clearance officers conduct statistics and count items.

According to the design documents, the road connecting to Lao Cai station and station square affects 8 households in Son Man 1 village and Hong Giang village, Lao Cai ward.

To ensure that the statistics and counting work is carried out publicly, transparently, and with the right subjects, the officers of the Project Management Board and representatives of households have reviewed and declared each item in detail according to current regulations of law.

baolaocai-br_galaocai-2.jpg
Lao Cai - Coc San Regional Project Management Board held a meeting to inform households about the project.

Previously, the Lao Cai - Coc San Regional Project Management Board held a meeting to publicize project information, compensation and site clearance policies, and resettlement locations; and directly answered people's questions related to compensation and site clearance support policies.

Households in the affected area all agree with the State's policy and hope that relevant agencies will speed up the resettlement process so that people can soon stabilize their lives.

The early completion of the statistics and land clearance work for the road connecting to Lao Cai station and the square will create favorable conditions for the groundbreaking of Lao Cai station on December 19, meeting the plan as directed by the Prime Minister .

baolaocai-br_galaocai-3.jpg
Households in the affected area.

The Lao Cai - Hanoi - Hai Phong railway project starts at the cross-border rail connection point (Lao Cai province); ends at Lach Huyen station (Hai Phong city), 419 km long, with a total investment of more than VND 203,200 billion (equivalent to USD 8.37 billion). The route has 18 stations, including 15 mixed stations for passenger and freight trains and 3 train-making stations.

The railway has a design speed of 160 km/h for the Lao Cai station - Lach Huyen port station section, 80 km/h for the Lao Cai - branch sections, and 120 km/h for the section passing through Hanoi and coinciding with the eastern belt railway.

The project consists of 10 components, of which Component Project 1 invests in infrastructure connecting stations and station squares, with a total investment of nearly VND2,300 billion, starting on December 19. Component Project 2 builds railway works, with a total investment of VND155,500 billion, starting at the end of 2026 and completing in 2030. In addition to the two construction projects, the project also includes 7 site clearance projects and one power infrastructure relocation project.

Source: https://baolaocai.vn/thong-ke-kiem-dem-giai-phong-mat-bang-khu-vuc-ga-lao-cai-post886977.html


Comment (0)

No data
No data

Same tag

Same category

Buckwheat flower season, Ha Giang - Tuyen Quang becomes an attractive check-in spot
Watching the sunrise on Co To Island
Wandering among the clouds of Dalat
The blooming reed fields in Da Nang attract locals and tourists.

Same author

Heritage

Figure

Enterprise

Vietnamese model Huynh Tu Anh is sought after by international fashion houses after the Chanel show.

News

Political System

Destination

Product