Vietnam.vn - Nền tảng quảng bá Việt Nam

Develop a weekly progress plan to speed up the disbursement of public investment capital from now until the end of 2025.

That was the direction of Vice Chairman of the Provincial People's Committee Nguyen Cong Hoang at a meeting with leaders of relevant departments, branches and localities on the morning of October 28, to assess the implementation and disbursement of public investment capital plans for projects in the eastern region of Quang Ngai province.

Việt NamViệt Nam28/10/2025

Vice Chairman of the Provincial People's Committee Nguyen Cong Hoang chaired the meeting.

Speaking at the meeting, the Vice Chairman of the Provincial People's Committee requested departments, branches and localities to urgently review the list of works and projects, specifically assess the implementation status of each project, thereby clearly identifying the causes of slow progress and proposing solutions to overcome them. The goal is to accelerate the implementation and disbursement of the public investment capital plan from now until December 31, 2025, ensuring the completion of assigned targets.

The total capital plan for 2025 for the eastern region of the province is 5,557 billion VND, including: national target program capital of 1,214 billion VND, public investment capital assigned to investors of 4,285 billion VND and other development investment capital of 58 billion VND.

The leaders of the Department of Finance reported on the disbursement results in the Eastern localities as of October 24, 2025.

As of October 24, 2025, investors have been assigned VND 4,285 billion, of which VND 1,570 billion has been disbursed, reaching 37% of the plan. Specifically, the provincial departments, branches and sectors disbursed VND 1,437/4,125 billion (reaching 35%), the local sector disbursed VND 134/160 billion (reaching 83%). The remaining undisbursed capital is VND 2,715 billion.

According to the assessment, the biggest problem currently facing projects in the Eastern region is compensation and site clearance. The slow implementation of the project is due to many reasons: determining the land use origin of households is complicated, land has been transferred many times; land recovery dossiers must be carried out through many steps, causing time delays; some investors and units implementing site clearance are not resolute, leading to delays in handing over the site to the construction unit.

Vice Chairman of the Provincial People's Committee Nguyen Cong Hoang gave a speech at the meeting.

Vice Chairman of the Provincial People's Committee Nguyen Cong Hoang requested relevant departments, branches, localities and units to concentrate maximum resources and make efforts to carry out compensation and site clearance work to promptly hand over the site to project construction units. Departments, branches and sectors need to increase support for investors and localities during the implementation process, sharing with localities according to the motto "holding hands and showing work"; investors must proactively coordinate closely and accompany local authorities and relevant units to promptly remove difficulties and obstacles.

At the same time, it is necessary to strengthen dialogue, support people, quickly resolve land complaints, and identify compensation and site clearance as key bottlenecks that need to be focused on removing during project implementation.

Meeting scene

The Vice Chairman of the Provincial People's Committee also assigned investors to proactively review and report to the Department of Finance to request the Provincial People's Committee to transfer capital between projects of similar nature before October 30, 2025; prioritize debt payment for completed volumes, and balance and regulate capital sources promptly and reasonably. It is necessary to develop a disbursement schedule for each specific project by week and month to speed up the disbursement of public investment capital from now until the end of the year, ensuring the completion of the disbursement target higher than the national average.

For projects using land use revenue in 2025, units need to urgently review and cut unnecessary projects to reduce total public investment capital, focus resources on disbursing central budget capital and speed up the implementation of national target programs.

Source: https://quangngai.gov.vn/tin-tuc/xay-dung-ke-hoa-ch-tien-n-do-theo-tua-n-de-da-y-nhanh-gia-i-ngan-vo-n-da-u-tu-cong-tu-nay-de-n-cuo-i-nam.html


Comment (0)

No data
No data

Same category

Dong Van Stone Plateau - a rare 'living geological museum' in the world
Watch Vietnam's coastal city make it into the world's top destinations in 2026
Admire 'Ha Long Bay on land' just entered the top favorite destinations in the world
Lotus flowers 'dyeing' Ninh Binh pink from above

Same author

Heritage

Figure

Enterprise

High-rise buildings in Ho Chi Minh City are shrouded in fog.

News

Political System

Destination

Product