| On December 10th, the Provincial People's Council voted to approve the draft Resolution on the investment policy for the Long Hung Bridge ( Dong Nai 2 Bridge) construction project under the public-private partnership model. Photo: Cong Nghia |
The project has a total investment of nearly 11.5 trillion VND, under the PPP model, BT contract, and will be paid for with revenue from the auction of public land funds or public investment capital.
The project belongs to group A, special-grade bridge and road works, with a total length of about 9.8km, of which Dong Nai 2 bridge is about 3.5km long, cross-section of 36m, design speed of 80km/h. The starting point is from Long Phuoc ward ( Ho Chi Minh City), the end point connects to Bien Hoa - Vung Tau expressway at Tam Phuoc ward and An Phuoc commune (Dong Nai province). The implementation period is 2026-2028.
![]() |
| The Dong Nai Bridge is currently operating beyond its designed capacity. Photo: Contributor. |
The project selected an investor under special circumstances due to its urgent nature. The resolution required the investor to reduce the BT contract value by at least 5% to ensure economic efficiency.
![]() |
| Project alignment for the Dong Nai 2 Bridge. Photo: Contributor. |
This is one of the necessary and urgent projects to strengthen the connection between Dong Nai and Ho Chi Minh City, helping to reduce the load on existing routes and meet the infrastructure needs when Long Thanh Airport is in operation. The implementation of Dong Nai 2 Bridge plays an important role in promoting economic growth, urban development and enhancing the competitiveness of Dong Nai, Ho Chi Minh City and the whole region. The project currently has an investor proposed for implementation.