![]() |
| The project to upgrade and expand provincial road 753 and build Ma Da bridge, the section passing through Tan Loi commune ( Dong Nai province) is under construction. Photo: Pham Tung |
More than 6 trillion VND still needs to be disbursed
In 2025, the provincial People's Committee has allocated nearly 37 trillion VND for public investment capital in the province. Of which, the capital plan assigned by the Prime Minister is nearly 32 trillion VND and the capital plan additionally assigned by the provincial People's Committee is more than 5 trillion VND.
As of November 25, 2025, the total disbursed public investment capital in the province was nearly 16 trillion VND, reaching nearly 43% of the capital plan assigned by the province. If not counting the capital plan of more than 9.2 trillion VND (including more than 8 trillion VND of the North-South Expressway Project, West section Gia Nghia - Chon Thanh, which was allowed by the National Assembly to extend the disbursement period until the end of 2026 and the newly assigned additional plan of 1.2 trillion VND), the capital disbursement rate of Dong Nai province up to that time reached more than 57% of the capital plan assigned by the province, higher than the average disbursement rate of the whole country (56.6%). Meanwhile, if calculated according to the capital plan assigned by the Prime Minister, the public investment disbursement rate of Dong Nai province reached 70% of the plan.
According to the Department of Finance, in recent times, many investors have made great efforts to accelerate the disbursement of public investment capital. Of the total 41 investors assigned by the Provincial People's Committee with capital plans for 2025, as of November 25, 2025, 29 units have a capital disbursement rate higher than the national average rate. Of which, 4 units with large capital and high average disbursement rate are: Project Management Board of Region 1 (Bien Hoa) achieved 93% of the plan, Project Management Board of Region 7 (Xuan Loc) achieved 83% of the plan, Project Management Board of Dong Phu region achieved 79% of the plan and Land Fund Development Center, Nhon Trach branch achieved 74%.
According to Mr. Tran Anh Tu, Deputy Director of the Department of Finance, with the total capital disbursed up to November 25, to complete the target of disbursing all public investment capital according to the plan assigned by the Prime Minister, after deducting the planned capital of more than 9.2 trillion VND of the North-South Expressway Project, West section Gia Nghia - Chon Thanh and additional capital, in the remaining time of 2025, Dong Nai province must complete the disbursement of more than 6.7 trillion VND.
Race against time
Director of Project Management Board of Region 1 Nguyen Ton Trong said: In 2025, the total capital allocated according to the unit's plan is 730 billion VND. As of mid-November 2025, the unit has disbursed more than 90% of the capital plan. With about 73 billion VND remaining capital, the unit is accelerating and making efforts to complete the disbursement to achieve the 2025 plan target.
"The remaining capital is being focused on disbursing for projects to build roads and embankments along the Dong Nai River; build four schools and five medical stations," said Mr. Trong.
According to the Department of Finance, as of November 25, 2025, there are 4 units in the province with low capital disbursement rates, including: Project Management Board of Region 10; Land Fund Development Center, Binh Long branch (due to newly added capital plan); Provincial Land Fund Development Center and Department of Industry and Trade.
In 2025, according to the adjustment of the public investment plan, the Dong Nai Provincial Land Fund Development Center was assigned nearly VND 1.7 trillion to implement 9 projects. By the end of November 2025, the unit had disbursed more than VND 780 billion.
Deputy Director in charge of the Provincial Land Fund Development Center Mai Phong Phu said: The remaining capital that needs to be disbursed by the unit by the end of 2025 is more than 900 billion VND. The unit has planned to complete the disbursement in December 2025. Thereby, completing the target of disbursing 100% of the capital allocated according to the 2025 plan.
According to the Department of Finance, the remaining capital that Dong Nai province needs to disburse to complete the disbursement target of 100% of the capital plan assigned by the Prime Minister in the remaining time of 2025 is relatively large. Therefore, it is necessary to have high determination from all departments, branches, localities, investors and related units, especially investors with large planned capital in 2025 such as: Provincial Construction Investment Project Management Board; Provincial Land Fund Development Center; Project Management Board of regions 5, 6, 10; Nhon Trach Branch Land Fund Development Center; Provincial Police; Provincial Military Command.
Pham Tung
Source: https://baodongnai.com.vn/kinh-te/202512/chang-cuoi-hoan-thanh-muc-tieu-giai-ngan-von-dau-tu-cong-0a228a1/











Comment (0)