Vietnam.vn - Nền tảng quảng bá Việt Nam

Ensuring the Hong Linh Town belt road project is completed on time

Việt NamViệt Nam06/10/2023

Determined to complete the ring road project according to the plan, the People's Committee of Hong Linh town (Ha Tinh) has focused on speeding up site clearance and handing over clean land to the construction unit on time.

VIDEO: Contractors rush to construct the Hong Linh Town belt road project

The Hong Linh Town Belt Road Project (from National Highway 8 to Tien Son Road) has a total investment of 150 billion VND, invested by the Hong Linh Town People's Committee, with a length of nearly 3km, and a 30m wide asphalt road surface. The project started construction in December 2022.

Ensuring the Hong Linh Town belt road project is completed on time

The shape of Hong Linh Town belt road is gradually taking shape.

The Hong Linh Town Ring Road project passes through 2 wards, of which Duc Thuan Ward has 103 affected households, Trung Luong Ward has 75 affected households. To ensure the progress of the project, in recent times, the People's Committee of Hong Linh Town has mobilized the participation of Party committees at all levels, the government, the entire political system and actively mobilized people's consensus, and promoted site clearance work. Thanks to that, the investor ensures the progress of site clearance, handing over clean land for the contractor to speed up the construction progress as committed.

Ensuring the Hong Linh Town belt road project is completed on time

To ensure progress and take advantage of favorable weather, Nhu Nam Company Limited mobilized vehicles and machinery to construct the items.

Mr. Ton Quang Ngoc - Vice Chairman of Hong Linh Town People's Committee said: "Along with promoting propaganda work, the town also publicly disclosed information about the project, publicly announced the State's compensation and support policies for site clearance for the project. The town has directed specialized agencies and localities to focus on reviewing the land status, declaring, classifying, and providing information on land plot measurements to each household so that people know clearly the area of ​​their land in the project and need site clearance. At the same time, organize meetings with people, publicly disclose the measurement results so that households related to the project can directly compare, reflect, reach consensus and finalize the data. Up to now, the project has cleared the land of 177/178 households".

Mr. Tran Thai Thinh in Thuan Hoa residential group - Duc Thuan ward said: "My family is one of 103 local households affected by the belt road project, having to clear more than 600m2 of agricultural land. When we heard about the project and were informed by Duc Thuan ward officials about the compensation and clearance policy, we completely agreed and quickly handed over the land to implement the project."

Ensuring the Hong Linh Town belt road project is completed on time

The bridge and culvert system on the Hong Linh Town belt road project has been basically completed.

The project of the ring road of the town aims to expand the urban area of ​​Hong Linh town to the West, connecting National Highway 8 with National Highway 1 through the main road of Hong Linh town (being invested from the capital of the Basic Infrastructure Project for the comprehensive development of Nghe An, Ha Tinh, Quang Binh and Quang Tri provinces - BIIG2); creating land fund for urban development and attracting investment for Hong Linh town.

Currently, Nhu Nam Company Limited (Hong Linh Town) is taking advantage of favorable weather to urgently speed up the construction progress of the items. With the motto "handing over the site to where, construction to where", the company is focusing on completing the drainage system and the roadbed.

Ensuring the Hong Linh Town belt road project is completed on time

Up to now, the roadbed embankment project has been completed by the contractor at 75% of the volume.

To ensure the set progress, the unit makes a real-time chart at the construction site, maintains a daily reporting regime to closely control the actual construction with the project documents. Mr. Mai Xuan Phu - technical officer, Nhu Nam Company Limited said: The unit is constructing the K95, K98 roadbed embankment, reaching 75% of the volume and basically completing the works on the route (drainage, drainage) with an estimated volume value of 35 billion VND, reaching about 30.4% of the total contract value. The project is expected to be completed in October 2025. All construction stages are closely monitored and standardized to ensure the requirements and objectives of the project.

In the coming time, the Town People's Committee will continue to strengthen the inspection and supervision of contractors during the construction process to ensure the quality and progress of the project; at the same time, direct competent authorities and contractors to perform well the reporting and consulting work with superiors to promptly resolve problems during the project implementation and capital disbursement.

Mr. Ton Quang Ngoc

Vice Chairman of Hong Linh Town People's Committee

Nam Giang


Source

Comment (0)

No data
No data

Same tag

Same category

Cuc Phuong in butterfly season – when the old forest turns into a fairyland
Mai Chau touches the heart of the world
Hanoi pho restaurants
Admire the green mountains and blue waters of Cao Bang

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product