Asphalt concrete pavement for the National Highway 8 overpass at the Dien Chau expressway project

Việt NamViệt Nam27/12/2023

The overpass at the intersection with National Highway 8, part of the Dien Chau - Bai Vot expressway project, is currently being paved with asphalt by Dai Hiep Co., Ltd., with the bridge surface and access roads to be opened to traffic in the coming days.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

On December 26th, taking advantage of the dry weather after a long period of heavy rain and low temperatures, Dai Hiep Co., Ltd. paved the surface of the overpass at the intersection of National Highway 8 with asphalt concrete, and the access roads to both ends of the bridge, to allow traffic to resume in the next two days.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

Engineer Vuong Dao Chau from Dai Hiep Co., Ltd. reported that bad weather has significantly affected the construction progress. The overpass at the National Highway 8 intersection is being prioritized to ensure traffic can resume within the next two days. Currently, the company has paved the bridge surface and is completing the approach roads at both ends.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

Opening the overpass at the National Highway 8 intersection will alleviate congestion on the service road previously used for the project's construction.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

The surface of the overpass on National Highway 8 was paved with C12.5 asphalt concrete a few days earlier. According to engineer Chau, the reason it was not possible to pave it continuously to open the bridge sooner was due to bad weather, which did not meet the requirements for asphalt paving.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

The bridge's railing system had already been installed by workers beforehand. This is an item that is not affected by the weather.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

The asphalt paving of the access roads to both ends of the bridge will be completed today (December 27th).

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

Tool for testing the thickness of hot mix asphalt.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

Engineers supervise the asphalt concrete compaction to ensure the quality of the road surface leading to the bridge.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

The overpass at the National Highway 8 intersection, along with the Hung Duc bridge (spanning the Lam River, connecting Nghe An and Ha Tinh provinces) and the rest stop, are three important components of the Dien Chau - Bai Vot expressway section passing through Ha Tinh.

Thảm bê tông nhựa cầu vượt QL 8 tại dự án cao tốc Diễn Châu - Bãi Vọt

At the access road to the roundabout at the Bai Vot - Ham Nghi expressway interchange, the construction unit is currently backfilling with sand; the box culvert system has been completed. Technical opening is expected in May 2024. If the Dien Chau - Bai Vot expressway is completed on schedule, from May 2024, people from Ha Tinh traveling to Hanoi and other northern provinces and cities can use National Highway 8, passing through the interchange, and then access the expressway.

The North-South Expressway Eastern section, phase 2017-2020, specifically the Dien Chau - Bai Vot section, has a total length of over 49km, passing through three districts in Nghe An province (44.4km) and Duc Tho district, Ha Tinh province (4.9km). It is one of three component projects invested under the public-private partnership (PPP) model.

In the phased construction, the project will have 4 lanes and a roadbed width of 17m, with sections where the roadbed is excavated and embanked having a width of 32.25m. In the completed phase, the project will be expanded to 6 lanes with a roadbed width of 32.25m.

The project has a total investment capital of over 11,157 billion VND in the phased implementation, of which 5,090 billion VND is mobilized by investors and over 6,067 billion VND is state capital.

The project commenced in 2021 and is expected to be completed in May 2024. The payback period for the operational costs is 16 years, 6 months, and 8 days.

According to baogiaothong.vn


Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product