Da Nang: By October 15, 2025, disbursement of public investment capital for transport and agricultural works will reach 68%.

DNO - On the morning of October 21, Vice Chairman of the City People's Committee Tran Nam Hung chaired a meeting with the Management Board of Investment and Construction Projects for Traffic and Agricultural Works in Da Nang on the operation situation and implementation of tasks in 2025.

Báo Đà NẵngBáo Đà Nẵng21/10/2025

MANAGEMENT BOARD
Working session scene. Photo: DAC MANH

Reporting at the meeting, Director of the Management Board of Investment Projects for Construction of Traffic and Agricultural Works in Da Nang (referred to as the Management Board) Nguyen Minh Huy said that since its establishment, the Management Board has completed 17/17 assigned tasks on time.

As of October 15, 2025, the disbursement rate of the public investment capital plan reached 68%, equivalent to VND 550,588/815,491 billion. It is expected that by January 31, 2026, 100% of the disbursement will be completed.

The Management Board is preparing to invest in 65 projects, of which 48 projects have been appraised by the Department of Finance through the investment policy appraisal report. 21/48 projects have approved the investment policy and 9/48 projects have approved the construction investment project.

Since the beginning of the year, the Management Board has carried out 38 projects (of which 4 projects have been completed, 10 new projects have been started; 24 projects are in transition, and 13 projects have been completed).

Three Project Management Boards for Construction Investment in affiliated areas have disbursed more than 336/616 billion VND (accounting for over 54%), are preparing to invest in 222 projects, and constructing 62 projects.

At the meeting, the Management Board proposed to reorganize the unit's operating model in a specialized direction; arrange locations for assembling surplus land for reuse; shorten procedures for granting mineral exploitation licenses; speed up compensation and site clearance so that the Management Board has space to construct projects to ensure progress.

Concluding the meeting, Vice Chairman of the City People's Committee Tran Nam Hung highly appreciated the results of the Management Board's performance; at the same time, he requested that in the coming time, the unit should continue to be proactive and determined in disbursing public investment capital, and propose effective solutions to quickly resolve difficulties in implementing assigned projects.

The Vice Chairman of the City People's Committee assigned the Department of Home Affairs to advise the City People's Committee to soon decide on the reorganization of the Management Board according to the model of the specialized construction investment project management board with affiliated professional departments.

For the People's Committees of communes and wards that meet the conditions, the establishment of Project Management Boards is allowed to speed up the progress of construction investment projects. For key projects in the area, the Management Boards need to be classified in order of priority and regularly report on the progress of implementation.

Propose that the Management Board coordinate with the City Land Fund Development Center and the People's Committees of communes and wards to have a detailed implementation plan; proactively develop resettlement project plans; speed up the progress of unfinished projects.

The Department of Agriculture and Environment shall coordinate with the Department of Finance to soon issue specific instructions related to land price determination for projects with compensation and clearance.

Promptly advise the City People's Committee on continuing to implement investment projects to build community activity houses that have been approved for investment policies, capital allocation, and projects to upgrade and renovate cultural works in the area.

Source: https://baodanang.vn/da-nang-den-ngay-15-10-2025-giai-ngan-von-dau-tu-cong-cac-cong-trinh-giao-thong-va-nong-nghiep-dat-68-3306895.html


Comment (0)

No data
No data

Same tag

Same category

'Rich' flowers costing 1 million VND each are still popular on October 20th
Vietnamese Films and the Journey to the Oscars
Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu

Same author

Heritage

Figure

Enterprise

Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp

News

Political System

Destination

Product