Huong Lo 2 Dong Nai: Progress of the 6,000 billion VND expressway connection project

The 15.5 km long Huong Lo 2 project in Dong Nai with a total capital of nearly 6,000 billion VND is being implemented, expected to reduce the load on National Highway 51 and promote riverside urban areas.

Báo Lâm ĐồngBáo Lâm Đồng09/12/2025

Overview of key projects

The People's Council of Dong Nai province has approved the investment policy for the construction project of Huong Lo 2 (section 2), connecting from National Highway 51 to Ho Chi Minh City - Long Thanh - Dau Giay Expressway. The project is implemented under the public-private partnership (PPP) method with a total estimated investment of nearly VND 6,000 billion, expected to be implemented in the period of 2025 - 2028.

Section 1 of Huong Lo 2 project is under construction, starting from National Highway 51.
Last November, the People's Council of Dong Nai province passed a Resolution approving the investment policy for the construction project of Huong Lo 2 (section 2) from National Highway 51 to Ho Chi Minh City - Long Thanh - Dau Giay Expressway under the public-private partnership (PPP) method. The project is divided into 3 sections, of which section 1 from National Highway 51 to An Hoa 2 Bridge is nearly 2 km long; section 2 from An Hoa 2 Bridge to Vam Cai Sut Bridge is about 6.2 km long; section 3 from Vam Cai Sut Bridge to Ho Chi Minh City - Long Thanh - Dau Giay Expressway is about 7.5 km long. In the picture is section 1, starting from National Highway 51, currently under construction.

When completed, the entire Huong Lo 2 route will be about 15.5 km long, a group A project, a level 1 project. The route passes through the wards and communes of Tam Phuoc, Long Hung, and An Phuoc of Dong Nai province, with a land use demand of more than 55.3 hectares and affects about 244 households.

Investment scale and divergence

The project is divided into two main component projects:

  • Component project 1: Implement compensation, support and resettlement with a total investment of nearly 574 billion VND from the province's public investment capital.
  • Component project 2: Construction of a road with a total capital of more than VND 5,315 billion, implemented under a Build-Transfer (BT) contract and paid from the State budget through land auction revenue.
The intersection between National Highway 51 and Huong Lo 2, the starting point of the project.
National Highway 51 intersection with Huong Lo 2. The project is divided into two component project packages, of which component project 1 is compensation and resettlement support for Huong Lo 2 (section from National Highway 51 to Ho Chi Minh City - Long Thanh - Dau Giay Expressway) with a total investment capital of nearly 574 billion VND, from the public investment capital of Dong Nai province.

Technically, the route has a 54 m wide roadbed, including a 25 m wide main road, a 3 m median strip, 8 m wide parallel roads on each side, and other auxiliary items such as drainage and lighting systems.

Typical cross-section of Huong Lo 2 with 54 m wide roadbed and many items.
Of which, the main road is 25 m wide, the median strip is 3 m wide, the parallel road on each side is 8 m wide, the median strip on each side is 2.75 m wide, the sidewalk on each side is 2 m wide, the roadbed is 54 m wide. In addition, there are intersections on the route.

Construction progress update

The project is being implemented in several phases. Section 1 from National Highway 51 to An Hoa 2 Bridge (nearly 2 km long) started construction at the end of 2020 with a budget of more than 780 billion VND, expected to be completed by the end of 2025.

An Hoa 2 Bridge under package 5 has completed more than 90% of the construction volume.
Currently, for package 5 including An Hoa 2 bridge and the last 250m route, the construction has reached more than 90% of the contract volume. In which, An Hoa 2 bridge has completed pouring the concrete part of the bridge deck, is deploying expansion joints and installing bridge railings. For the last part of the 250m route in Long Hung ward, the construction is implementing the earthwork, leveling the slope, and digging the base of the slope tray.

Meanwhile, the Vam Cai Sut bridge was completed in December 2024 and accepted in July 2025. However, because the road connecting the bridge to the Ho Chi Minh City - Long Thanh - Dau Giay expressway has not been built yet, this project cannot be effective at present.

Vam Cai Sut Bridge has been completed but there is no synchronous connecting road.
Regarding the Vam Cai Sut bridge on Huong Lo 2 road, construction was completed in December 2024 and accepted for use in July 2025. However, currently, the bridgehead in Tam Phuoc ward to the Ho Chi Minh City - Long Thanh Dau Giay expressway has no connecting road, so the Vam Cai Sut bridge cannot be used effectively.

Impact on the economy and real estate market

The investment in completing Huong Lo 2 is expected to complete the traffic system according to the planning of Dong Nai province, share traffic and reduce pressure on National Highway 51. At the same time, the project also forms a road axis along the Dong Nai river, creating momentum for socio-economic development and modern urban areas.

Huong Lo 2 is expected to promote the development of urban areas along the Dong Nai River.
The investment in completing Huong Lo 2 route from National Highway 51 to Ho Chi Minh City - Long Thanh - Dau Giay Expressway aims to gradually complete the traffic system according to Dong Nai province's planning. In addition, the province will form a road along the Dong Nai river to promote the development of modern riverside megacities, creating conditions for socio-economic development of the province; sharing traffic and reducing traffic pressure on National Highway 51. Along with that, a series of real estate projects in subdivision C4 will also benefit directly from this project, such as Aqua City of Novaland ; Waterfront of Nam Long; Long Hung residential area of ​​Donacoop...

This transport infrastructure is also expected to have a positive impact on the regional real estate market, especially large projects such as Aqua City, Waterfront and Long Hung residential area.

Note: Project information may change according to planning adjustment decisions of competent authorities.

Source: https://baolamdong.vn/huong-lo-2-dong-nai-tien-do-du-an-6000-ty-ket-noi-cao-toc-409193.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC