At the Gia Binh International Airport construction investment project, units and localities declared nearly 6,700/7,980 households and individuals with an agricultural land area of about 818 hectares; made advance payments of more than VND 2,405 billion to about 4,825 households with an area of 533.6 hectares in Luong Tai, Gia Binh, and Nhan Thang communes; declared and inventoried about 7,500 graves. Units are implementing the inventory of residential land area...
Investors and contractors are focusing on human resources, equipment for site leveling and preparation work to deploy the VIP terminal, air traffic control tower and runway projects.

Based on the progress reports of relevant units, Secretary of the Bac Ninh Provincial Party Committee Nguyen Hong Thai emphasized that site clearance is of great importance and is also the biggest challenge in ensuring the progress of the Gia Binh International Airport construction project to serve the APEC Summit in 2027.
The Secretary of the Bac Ninh Provincial Party Committee requested units and localities to speed up the site clearance work, especially urgently invest in the construction of resettlement projects so that people can soon hand over the site and move to stabilize their lives. Investors and construction units focus on implementing in areas with available site, completing procedures and work records according to the proposals of the industry and localities.
Provincial Party Secretary Nguyen Hong Thai affirmed that Bac Ninh will meet with central ministries and branches to develop mechanisms and policies to ensure the legitimate rights of people in the project area; at the same time, the province always accompanies investors, removes difficulties, and is determined to deploy and implement the project on schedule.
For component project 2.3 of the investment project to build the 4th ring road - Hanoi Capital region section through Bac Ninh province, the construction volume reached more than 966/2,307.9 billion VND, equivalent to nearly 42% of the contract value. Contractors are facing difficulties due to lack of soil for filling and crushed stone; the announcement of material prices is slow and not close to market prices...
Through the inspection, Provincial Party Secretary Nguyen Hong Thai requested investors and contractors to mobilize maximum human and material resources to speed up construction progress, ensure quality, labor safety and site hygiene.
The Provincial Party Secretary assigned the relevant departments and branches to continue to find solutions to remove difficulties for contractors in terms of construction material sources; when the market fluctuates continuously, it is necessary to promptly announce material prices and close to market prices; advise the Provincial People's Committee on how to handle the organic soil source (not being used for roadbed construction) remaining at the construction site to facilitate the construction unit as well as surrounding projects that need to level the ground.
Source: https://daibieunhandan.vn/khan-truong-trien-khai-cac-khu-tai-dinh-cu-phuc-vu-cong-tac-gia-phong-mat-bang-cang-hang-khong-quoc-te-gia-binh-10397905.html






Comment (0)