According to the People's Committee of Ha Dong commune, on October 10th, the locality will forcibly reclaim land to implement the Project to renovate and upgrade Provincial Road 396 (the section connecting from Road 391 to Road 390) Phase 1 through Ha Dong commune.
The project requires the acquisition of land from 237 households, and to date, 4 households have yet to comply with the land handover requirements, affecting the construction progress.
The People's Committee of Ha Dong commune has sought guidance from the city on land clearance for the project, and has issued plans and decisions to forcibly reclaim land from 4 households in accordance with the procedures and regulations of the law. The People's Committee of Ha Dong commune has notified the households whose land is to be reclaimed to proactively move their assets.
The project to renovate and upgrade Provincial Road 396 (the section connecting Provincial Road 391 to Provincial Road 390), phase 1, is approximately 1.87 km long (located in Ha Dong commune) and has a total investment of over 54.6 billion VND from the former Hai Duong provincial budget, with an implementation period of 2023-2025.
MINH NGUYENSource: https://baohaiphong.vn/ngay-10-10-xa-ha-dong-se-cuong-che-thu-hoi-dat-lam-duong-396-keo-dai-522912.html