Removing obstacles and ensuring the progress of 4 expressway projects.

Deputy Prime Minister Bui Thanh Son requested decisive action to remove obstacles and ensure the progress of the Tuyen Quang - Ha Giang, Dong Dang - Tra Linh, and Huu Nghi - Chi Lang expressway projects.

Báo Hải PhòngBáo Hải Phòng12/12/2025

Tuyen Quang-Ha Giang Expressway. (Photo: Quoc Khanh/VNA)
Tuyen Quang- Ha Giang Expressway. (Photo: Quoc Khanh/VNA)

The Government Office issued document No. 12307/VPCP-CN dated December 11, 2025, announcing the directive of Deputy Prime Minister Bui Thanh Son regarding the review and resolution of difficulties and obstacles at four expressway projects: Tuyen Quang - Ha Giang section through Ha Giang province (now Tuyen Quang province), Tuyen Quang - Ha Giang section through Tuyen Quang province (formerly), Dong Dang - Tra Linh, and Huu Nghi - Chi Lang.

Considering the report and recommendations of the Ministry of Construction on the implementation status and results of resolving difficulties and obstacles at 4 expressway projects: Tuyen Quang - Ha Giang section through Ha Giang province (now Tuyen Quang province), Tuyen Quang - Ha Giang section through Tuyen Quang province (formerly), Dong Dang - Tra Linh, and Huu Nghi - Chi Lang, from Inspection Team No. 5, Deputy Prime Minister Bui Thanh Son has the following opinion:

Government leaders have inspected the sites and issued numerous specific directives to resolve difficulties and obstacles, accelerate progress, and complete the projects. Provincial People's Committees have submitted documents registering for inauguration, opening to traffic, and commencement of construction on December 19, 2025. However, some projects still face outstanding issues, especially land clearance and relocation of technical infrastructure, which have been postponed multiple times and remain unfinished to this day.

To ensure that projects are completed on schedule as committed, the Deputy Prime Minister requested that localities, agencies, and units urgently carry out their assigned tasks.

Regarding land clearance, resettlement, relocation of technical infrastructure, material mines, and waste disposal sites, the Chairpersons of the People's Committees of Tuyen Quang and Lang Son provinces focused on directing, decisively urging, inspecting, and thoroughly resolving all outstanding issues and obstacles; and considering the responsibility of organizations and individuals who failed to complete their tasks within the required timeframe, affecting the progress of the projects.

Before December 18, 2025, Tuyen Quang province will complete the relocation of the remaining 3 power line locations; Lang Son province will complete the relocation of the remaining households and thoroughly resolve the causes of people obstructing construction at the Dong Dang - Tra Linh Project; and complete the relocation of power lines and hand over the remaining waste disposal site at the Huu Nghi - Chi Lang Border Gate Project.

Regarding construction work, localities, project owners/management boards, investors, project enterprises, consultants, and contractors should focus intensely, continue to enhance their sense of responsibility, and strive with even greater determination to complete and open the projects to traffic, ensuring quality, safety, and environmental hygiene before December 19, 2025, especially the priority sections that need to be put into use and operation soon to serve the people during the upcoming holidays (New Year's Day 2026, Lunar New Year of the Horse...).

The Chairpersons of the People's Committees of Tuyen Quang, Cao Bang, and Lang Son provinces are instructed to carefully review the processes, procedures, and conditions to ensure that the inauguration, opening to traffic, commencement, and groundbreaking ceremonies for projects on December 19, 2025, comply with the law.

According to Vietnam+

Source: https://baohaiphong.vn/thao-go-vuong-mac-bao-dam-tien-do-4-du-an-duong-bo-cao-toc-529414.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product