Urgent and drastic efforts to ensure construction progress of National Highway 28B Project

On the afternoon of October 17, Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep and the working delegation inspected the site to promote the construction progress of the project to upgrade and expand National Highway 28B.

Báo Lâm ĐồngBáo Lâm Đồng17/10/2025

Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep discussed and requested more efforts to speed up the progress.
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep discussed and requested relevant units to make more efforts to speed up the project's construction progress.

The working group surveyed the entire project route, starting from the Luong Son - National Highway 1 intersection to the end of the route.

Through on-site inspection, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep assessed that although the project progress has changed, it is still slow, many construction items are still in disarray, while site clearance work has not been completed along the entire route. Some sections have been handed over but there are no construction workers.

Vice Chairman of the Provincial People's Committee discussed the work of relocating infrastructure on the route.
Vice Chairman of Lam Dong Provincial People's Committee discussed the work of relocating infrastructure on the route.

According to the design, the National Highway 28B Upgrade and Expansion Project is about 68km long, of which the Km0-Km28 section is a level 3 plain road, the Km28-Km69 section is a level 3 mountainous road, with asphalt concrete road surface structure.

The project has so far only paved 37.65km of asphalt concrete, and many sections are still covered with dirt and rocks.
The project has so far only paved 37.65 km of asphalt concrete, with many sections still covered with dirt and rocks.

Lam Dong Department of Construction said that up to now, the locality has reclaimed and mobilized people to hand over the land for 62/68km (91.17%), the remaining 6km are mainly densely populated sections in Luong Son commune.

The project to upgrade and expand National Highway 28B was started in April 2024.
The project to upgrade and expand National Highway 28B was started in April 2024, but many sections are still in disarray.

Representatives of the People's Committees of the communes said that site clearance work still faces many difficulties, which is the main reason for the slow progress of the project.

The project is about 68km long, and is currently progressing quite slowly due to many reasons.
The project is about 68km long, and is currently progressing quite slowly due to many reasons, making it unlikely to be completed by the end of 2025 as planned.

After the field survey, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep had a working session with Project Management Board 5, departments and localities where the project passes through.

Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep worked with Project Management Board 5, departments and localities where the project passes through.
Working session scene

According to the report of Project Management Board 5, up to now, the project implementation value has reached about 615/1,083 billion VND (excluding contingency), equivalent to 57% of the contract value. Of which, the asphalt concrete pavement has reached 37.65 km (54%), while the bridge and alignment works are still under construction but the progress is still slow.

The bridge alignment project is under construction, but progress is quite slow.
The bridge alignment project is under construction, but progress is quite slow.

At the meeting, representatives of the People's Committees of the communes reported on the progress of site clearance and the difficulties that caused the work to be slow in some sections. The construction unit admitted that some items were still slow, and pledged to speed up the progress in areas where the site was available; at the same time, it recommended that the province promptly hand over the remaining areas.

Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep acknowledged the efforts of localities and the Project Management Board in removing difficulties and promoting progress. Up to now, the communes have basically resolved most of the problems related to land clearance, relocation of electric poles and clearance of areas related to railway signals.

Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep emphasized that accelerating the progress of the National Highway 28B upgrading and renovation project is an urgent task, contributing to ensuring convenient traffic, inter-regional connectivity and promoting socio -economic development.

The Ministry of Construction also requested that the Project must be completed in 2025. Therefore, he requested that departments, branches, localities and construction units make more efforts and implement urgently and resolutely to ensure progress.

The Vice Chairman of the Provincial People's Committee requested the communes, the Compensation and Site Clearance Board and the Project Management Board to complete all site clearance work in October. In particular, the investor was required to review and reorganize construction on site; strictly handle contractors who do not implement on schedule; and at the same time, have alternative plans to speed up the project implementation progress.

Source: https://baolamdong.vn/no-luc-trien-khai-khan-truong-quyet-liet-de-dam-bao-tien-do-thi-cong-du-an-quoc-lo-28b-395953.html


Comment (0)

No data
No data

Same tag

Same category

Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp

Same author

Heritage

Figure

Enterprise

Com lang Vong - the taste of autumn in Hanoi

News

Political System

Destination

Product