Vice Chairman of the Provincial People's Committee Ngo Cong Thuc inspected component project 1 of the Chau Doc - Can Tho - Soc Trang expressway project, phase 1, the section passing through An Giang province.
During an on-site inspection of component project 1 of the Chau Doc - Can Tho - Soc Trang Expressway Project, phase 1, the section passing through An Giang province, comprising 4 contract packages with a total length of 57km, all contractors were present at the construction site and reported progress that met the requirements of the set plan.
However, in order to meet the Prime Minister 's directive to complete the project by December 19, 2025, the construction units need to continue their efforts and propose additional technical solutions to shorten the implementation time.
Vice Chairman of An Giang Provincial People's Committee Ngo Cong Thuc presents gifts to construction workers at the project site.
Vice Chairman of the An Giang Provincial People's Committee Ngo Cong Thuc requested that state management agencies and investors coordinate closely to ensure that materials are supplied fully, promptly, and transparently. Beyond simply increasing shifts and overtime, units should focus on proposing and applying innovative technical solutions to shorten construction time while still meeting quality and safety requirements.
In particular, Comrade Ngo Cong Thuc requested that contractors, investors, and specialized departments clearly define specific technical solutions, prioritizing research into changing materials and improving road surface structure to suit actual conditions and optimize progress.
This process requires exchange and agreement among all stakeholders, as well as proactive consultation with the Ministry of Construction regarding major proposed changes, ensuring that all adjustments do not negatively impact the quality, progress, or budget of the project.
We request that all relevant units seriously implement these directives, coordinate effectively, and use actual results as a measure of responsibility and work efficiency.
Vice Chairman of the Provincial People's Committee Ngo Cong Thuc inspects the project to upgrade and expand Provincial Road 941.
To date, the total progress of the four main construction packages has reached 57.87% (exceeding the contract value by approximately 0.02%). This corresponds to an estimated completed work value of approximately VND 4,855 billion out of VND 8,391 billion.
On this occasion, Working Group No. 4 inspected key projects in An Giang province, including: the Provincial Road 941 (extended section) project in Binh Duc ward and the project to upgrade and expand Provincial Road 941 (section from Bridge 16 to the intersection of 3 Thang 2 Street and Hung Vuong Street, Tri Ton commune).
Vice Chairman of the Provincial People's Committee Ngo Cong Thuc inspected the project to upgrade and expand Provincial Road 941 ( section from Bridge 16 to the intersection of 3 Thang 2 Street and Hung Vuong Street).
Regarding the extension of Provincial Road 941, Vice Chairman of the An Giang Provincial People's Committee Ngo Cong Thuc stated that land clearance is a key factor in accelerating construction progress and capital disbursement. Therefore, decisive solutions are needed to address this issue.
Regarding the road from Bridge 16 to Tri Ton Market, part of the Provincial Road 941 upgrade and expansion project (the section from Bridge 16 to the intersection of 3 Thang 2 Street and Hung Vuong Street), although the length is not large, it is an important end point of the project, contributing to urban beautification in Tri Ton commune and disbursing investment capital for the locality this year. The comrade emphasized the significance of the project as a milestone to welcome the Provincial Party Congress, therefore the local government of Tri Ton commune should focus on land clearance as soon as possible.
Text and photos: PHUONG LAN