Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City's West Beltway 3: Changing but still slow

Five months after the Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc inspected the construction packages west of the Ho Chi Minh City Ring Road 3, the construction site has seen many positive changes. However, the progress is still difficult to meet the approaching technical traffic opening date.

Báo Tuổi TrẻBáo Tuổi Trẻ17/10/2025

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 1.

Construction machinery at the western section of Ring Road 3 in late September and early October 2025.

According to Tuoi Tre Online reporters, the construction sites of the XL06 to XL10 beltway 3 in Ho Chi Minh City in the first days of October have become bustling again. Engineers, workers and machines are working in many locations. Some important intersections and bridge piers have been erected, and the roadbed in many sections is being loaded, a clear change compared to 5 months ago.

However, in packages XL09 to XL10, there are still many sections of the foundation that have not been treated, with overgrown grass and intermittent ground. To proceed with the steps of loading, spreading crushed stone and completing the roadbed, a considerable amount of time is needed while the technical opening time is only more than 2 months away.

According to the progress report by the end of September, the total volume of the western packages (XL06 - XL10) has reached more than 58%. Of which, package XL10 is still the slowest package, only reaching more than 41% of the volume value.

In recent field trips and meetings, Ho Chi Minh City leaders have repeatedly asked investors and contractors to maximize resources, organize construction in "3 shifts, 4 teams", increase equipment and workers, and have backup plans in case of bad weather. The city also directed to strengthen inspection and supervision, and promptly handle bottlenecks.

The Traffic Department reported that it has coordinated with contractors and consultants to sign a "100-day sprint" competition agreement to speed up progress.

The units committed to focusing all resources and maintaining continuous construction to basically complete the project before December 19, 2025, according to the direction of the Prime Minister and the Ho Chi Minh City People's Committee.

Although the construction site west of Ring Road 3 is busier than 5 months ago, to reach the technical traffic opening milestone in December, contractors still have to "race with all their might" on the construction site.

Chairman of Ho Chi Minh City People's Committee: "The western section of Ho Chi Minh City's Ring Road 3 must be technically open to traffic by the end of December"

At the inspection on October 1, the HCM City Traffic Construction Investment Project Management Board reported that many sections of the route are still in the foundation loading stage, having only completed step 1. Some bridges are expected to be completed on December 19, while some sections may not be completed until January or February 2026.

Concluding the meeting, Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc emphasized: "The eastern elevated section must be operational in December, the western section must be technically open to traffic at the end of December. The Traffic Department and contractors must make maximum efforts to ensure progress."

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 2.

Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc pointed to the XL09 - XL10 package of the western Ring Road 3 project (on the map) and requested to ensure the technical traffic opening progress on December 19, 2025. Recorded at the construction site inspection on October 1.

Vành đai 3 TP.HCM - Ảnh 2.
Vành đai 3 TP.HCM - Ảnh 3.

Current status of the area adjacent to the XL9 package (Ring Road 3 - Tran Van Giau intersection) after 5 months.

Vành đai 3 TP.HCM - Ảnh 4.
Vành đai 3 TP.HCM - Ảnh 5.

A section of the roadbed at the XL10 package has been changed after 5 months. The construction unit is currently processing the foundation.

Vành đai 3 TP.HCM - Ảnh 6.

At the XL10 package, there are now more workers participating in construction than 5 months ago.

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 9.

Beltway 3 through Binh Chanh district (from Tran Van Giau street towards old Long An ) parallel to Kenh A street - Photo taken in May.

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 10.

After more than 5 months, this construction site has slightly changed in terms of layout, but construction activities have not yet taken place - Photo taken in early October.

Vành đai 3 TP.HCM - Ảnh 9.
Vành đai 3 TP.HCM - Ảnh 10.

The overpass section at the intersection of Ring Road 3 - Tran Dai Nghia has added a few more spans after 5 months.

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 13.

Panoramic view of the overpass at the intersection of Ring Road 3 - Tran Dai Nghia - Photo taken in early October.

Vành đai 3 TP.HCM phía tây: Chuyển mình nhưng còn chậm - Ảnh 14.

The work on the Ring Road 3 foundation at the construction site from Tran Dai Nghia to Thich Thien Hoa, towards the old Long An is still uneven and intermittent. Some sections are covered with green grass - Photo taken in early October.

Vành đai 3 TP.HCM - Ảnh 13.
Vành đai 3 TP.HCM - Ảnh 14.

Photo of Ring Road 3 intersection with Provincial Road 15 (first section of Ho Chi Minh City - Moc Bai Expressway) after 5 months has shown quite clear changes.

Vành đai 3 TP.HCM - Ảnh 15.
Vành đai 3 TP.HCM - Ảnh 16.

The foundation of this package has changed after 5 months. Previously, the Traffic Department reported that the bridge construction items of the Ring Road 3 project were still progressing well, but the road part was delayed due to lack of sand.

CHAU TUAN - LE PHAN

Source: https://tuoitre.vn/vanh-dai-3-tp-hcm-phia-tay-chuyen-minh-nhung-con-cham-20251017113211227.htm


Comment (0)

No data
No data

Same tag

Same category

Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp

Same author

Heritage

Figure

Enterprise

Com lang Vong - the taste of autumn in Hanoi

News

Political System

Destination

Product