Deputy Minister of Construction Nguyen Viet Hung and the working delegation inspected the progress of the Hoa Lien-Tuy Loan expressway project on July 17. (Photo: ANH DAO)

Deputy Minister Nguyen Viet Hung requested the construction unit to ensure technical traffic clearance before August 19 and prepare compensation plans for households whose land is being obstructed, hindering construction.

According to the representative of the Ho Chi Minh Road Project Management Board, the project's output has reached over VND502 billion, equivalent to 58.44% of the total value. The project is currently organizing 20 construction teams working in 3 continuous shifts, focusing on road surfaces, asphalt concrete, underpasses, and access roads...

However, there are still some problems, specifically: About 100m cannot be constructed due to 9 land records in the area connecting to DH2 road, causing traffic safety risks when put into operation. In Ba Na commune, many households protested the construction because they said that the vibrating roller activity caused cracks in the houses, this area is about 500m long and cannot be re-implemented.

The Ho Chi Minh Road Project Management Board proposed that the Ministry of Construction work with the leaders of Da Nang City to direct relevant units to hand over the clean site no later than July 20; at the same time, mobilize and handle the situation of people obstructing the construction before July 18 to ensure the traffic opening progress.

At the same time, it is recommended that the People's Committee of Da Nang City direct the Infrastructure Investment Project Management Board to prioritize speeding up procedures for the two resettlement areas, ensuring the disbursement of all allocated capital for site clearance.

Mr. Le Thanh Binh, Deputy Director of the Ho Chi Minh Road Project Management Board, said that contractors are focusing on the main road surface. If the weather is favorable, the entire road surface will be completed before August 15, and will be technically ready for traffic on August 19, 2025.

Deputy Minister of Construction Nguyen Viet Hung requested to speed up the progress and open the Hoa Lien-Tuy Loan expressway to traffic before August 19. (In photo: Hoa Lien-Tuy Loan expressway seen from above)

Currently, vehicles can travel the entire route on the 11.5km long asphalt concrete layer. The Hoang Van Thai intersection - once the most congested point - has also been resolved.

After listening to reports from investors, contractors and related parties, Deputy Minister Nguyen Viet Hung requested units to resolutely speed up progress, especially for sections where the site has been handed over and there are no more problems, then maximum human resources and equipment must be focused to implement construction.

The project is on the list of key projects to celebrate the National Day on September 2. Therefore, the main route must be completed and technically opened to traffic before August 19.

The Hoa Lien-Tuy Loan Expressway Project is 11.5km long, located in Da Nang City. The total investment is over 2.1 trillion VND (land clearance cost: 951.19 billion VND). The project will start construction in September 2023, the main expressway route will be completed by August 2025, and the entire project will be completed by November 2025.

According to nhandan.vn