Accompanying the delegation from Nghe An province was Comrade Nguyen Duc Trung - Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee.
| Minister of Industry and Trade inspects the construction site of the 500kV transmission line project, circuit 3, section through Nghe An. |
The 500kV circuit 3 transmission line from Quang Trach - Quang Binh to Pho Noi - Hung Yen is a key energy project, regularly supervised and directed by the State Steering Committee for National Important Programs, Works, and Projects.
| The construction site for laying the power line at anchor points 337-338 is located in Nam Thai commune, Nam Dan district, and is part of the Quang Trach - Quynh Luu component project. |
A delegation from the Ministry of Industry and Trade visited the site to directly inspect and encourage the team of workers and engineers who are constructing the power line at anchor points 337-338 in Nam Thai commune, Nam Dan district, part of the Quang Trach - Quynh Luu component project. This is the first location of the 500kV circuit 3 power line project passing through Nghe An province where power line installation is underway.
According to the plan, the cable laying at this location will begin on June 16th and be completed by June 19th. Because it runs above 220kV and 110kV power transmission lines, the operating unit must conduct rotational power outages during construction to ensure safety.
| The installation of the 337-338 anchorage point, located in Nam Thai commune, Nam Dan district, began on June 16th and is expected to be completed by June 19th. |
Reporting to Minister Nguyen Hong Dien, Chairman of the Provincial People's Committee Nguyen Duc Trung stated that Nghe An province has completed the handover of the land to the construction unit.
“The province has participated in supporting contractors in construction in accordance with the Prime Minister's '4 on-site' directive: On-site resources, on-site materials, on-site command, on-site logistics. The province is committed to accompanying investors and contractors in implementing the project in the spirit of the Prime Minister and the Minister,” added Chairman of the Provincial People's Committee Nguyen Duc Trung.
| Minister of Industry and Trade Nguyen Hong Dien and Chairman of the Provincial People's Committee Nguyen Duc Trung presented gifts to encourage the working spirit of the team of workers and engineers at the construction site. |
Minister of Industry and Trade Nguyen Hong Dien assessed that the workload in Nghe An is on schedule.
At the construction site at poles 337 and 338, Minister of Industry and Trade Nguyen Hong Dien presented gifts to encourage the working spirit of the engineering and construction team. He also expressed his hope that the contractor would overcome all difficulties related to terrain and weather conditions, and strive to complete the 500kV circuit 3 power line project on schedule, ensuring timely energization to serve the socio-economic development needs of the country.