On the afternoon of December 27th, the atmosphere at the Tan Son Nhat T3 terminal construction site was one of intense work. The project is currently in its "final sprint" phase, aiming for completion before April 30th, 2025.
Currently, there are more than 2,500 workers and engineers, and hundreds of machines and equipment working day and night at the Tan Son Nhat T3 terminal construction site - Photo: CHAU TUAN
The Airports Corporation of Vietnam (ACV) stated that Tan Son Nhat is one of the three most important and largest airports in the country. The construction of Terminal 3, with a capacity of 20 million passengers per year, aims to alleviate the burden on the currently overloaded Terminal 1 and improve service quality for the public.
Currently, the T3 terminal construction project has completed the concrete and structural work. Specifically, the 7,500-ton steel roof structure and 45,000 m² aluminum roof are 100% complete. The glass curtain wall is 94% complete and is expected to be fully finished in December 2024.
At the same time, many other components of Terminal 3 have been and are being completed. To date, the total volume has reached approximately 83%, with the goal of completing everything by April 30, 2025, for operation and exploitation.
Mr. Le Khac Hong, head of the Tan Son Nhat T3 terminal project management board, said the project has achieved good results in many aspects, including progress, construction quality, and labor safety.
"To inaugurate the project on April 30, 2025, we must complete it one month earlier, meaning we only have 90 days left to finish the construction. This is a huge challenge, requiring all relevant units to work together more diligently, strive harder, and be more determined."
Therefore, the site management team needs to pay special attention to and promptly resolve any problems arising during construction, creating the most favorable conditions for the contractors.
"We will mobilize all available resources and implement solutions to ensure the complete installation of equipment and the safe and high-quality commissioning and acceptance testing, guaranteeing the project's completion and commissioning," Mr. Hong said.
Current image of Tan Son Nhat T3 terminal:
The T3 terminal construction project comprises four main components: a passenger terminal, a multi-story parking garage combined with non-aviation services, an elevated walkway system in front of the terminal, and an aircraft parking apron, with a total investment of 10,990 billion VND - Photo: CHAU TUAN
The glass curtain wall section of Terminal 3 has reached 94% completion - Photo: CHAU TUAN
Many other items are also being expedited by the construction unit - Photo: CHAU TUAN
To speed up construction progress, contractors have adopted a method of dividing the construction into smaller teams, combined with fabricating steel structures at the factory - Photo: CHAU TUAN
Inside the passenger terminal, there is now a massive scaffolding system that allows workers to work safely at height - Photo: CHAU TUAN
The 7,500-ton steel roof structure is now complete - Photo: CHAU TUAN
Outside the passenger terminal, elevated bridges and viaducts are also under construction - Photo: CHAU TUAN
The investor stated that to ensure progress, the company requires contractors to follow the government 's directive of "overcoming the sun and rain, eating and sleeping quickly, working in 3 shifts and 4 teams, and working throughout holidays and Tet" - Photo: CHAU TUAN
Terminal T3 is the largest domestic passenger terminal in the country, with a capacity of 20 million passengers per year, and was built with an investment of nearly 11,000 billion VND from the Vietnam Airports Corporation (ACV) - Photo: CHAU TUAN
Launching a campaign to bring Terminal T3 to completion as soon as possible.
Later that same day, the Airports Corporation of Vietnam (ACV) held a ceremony to summarize the 90-day emulation campaign to complete the entire terminal roof, facade, and power supply of the project, and launched a 120-day emulation campaign to finish before April 30, 2025.
On behalf of the investor, Mr. Le Khac Hong commended the efforts of the contractors who responded to the emulation campaign, accelerated the construction progress, and brought the project to completion ahead of schedule.