The Project to Renovate and Upgrade National Highway 28B through Lam Dong Province was approved by the Ministry of Construction in Decision No. 1495/QD-BGTVT, dated November 16, 2023. The project has a route length of 68km, with a total investment of VND 1,435 billion.
The Project Investor is the Vietnam Road Administration. The unit directly managing the project is Project Management Board 5. The project started in April 2024, is expected to be completed in December 2025 and complete the project closing procedures in 2026.

Lam Dong Provincial People's Committee is the unit carrying out the site clearance work. The entire project has 980 affected cases. Up to now, the site clearance work has been completed for 62/68km, reaching 91.17%.

According to the investor's report at the site, up to now, the construction units are constructing on the site within the scope of the handed over site.
Construction progress of crushed stone mixture reached 44/62km; asphalt concrete pavement was compacted about 37/62km.

However, according to the management unit's report, in many sections the site has been handed over by the locality, but the construction progress has not met the requirements.
The reason is that in some sections, the construction unit has not fully arranged machinery, equipment and human resources at the construction site.



Source: https://baolamdong.vn/chu-tich-ubnd-tinh-lam-dong-ho-van-muoi-kiem-tra-du-an-quoc-lo-28b-397234.html