The project to renovate and upgrade National Highway 28B through Lam Dong province was approved by the Ministry of Construction in Decision No. 1495/QD-BGTVT, dated November 16, 2023. The project has a total length of 68km and a total investment of 1,435 billion VND.
The project's investor is the Vietnam Road Administration. The project is directly managed by Project Management Board 5. Construction commenced in April 2024, is expected to be completed in December 2025, and all project completion procedures will be finalized in 2026.

The People's Committee of Lam Dong province is the unit responsible for land clearance. The entire project affects 980 households. To date, land clearance has been completed for 62 out of 68 km, reaching 91.17%.

According to the investor's report from the site, the construction units are currently working on the site within the areas where the land has been handed over.
The construction progress for the crushed stone base layer has reached 44/62km; the compacted asphalt concrete paving has been completed for approximately 37/62km.

However, according to the management unit's report, in many sections where the land has been handed over by the local authorities, the construction progress has not met the requirements.
The reason is that in some sections of the route, the construction unit has not yet deployed sufficient machinery, equipment, and personnel on the construction site.



Source: https://baolamdong.vn/chu-tich-ubnd-tinh-lam-dong-ho-van-muoi-kiem-tra-du-an-quoc-lo-28b-397234.html