The total approved amount of temporary housing support is over 4.2 billion VND. Of which, the number of households in component project 1 is 69 cases with the amount of over 1 billion VND; the number of households in component project 2 is 201 cases with the amount of over 3.2 billion VND.
The Long Thanh District People's Committee announced that it has approved a plan to provide temporary housing support for 270 cases of land allocation for the Bien Hoa - Vung Tau Expressway project passing through the area. The total support amount is more than 4.2 billion VND, helping people reduce difficulties in handing over the land.
Temporary residence policy will help remove difficulties in site clearance.
Specifically, the number of households approved for temporary housing support for component project 1 is 69 cases, with a support amount of more than 1 billion VND; component project 2: 201 cases, with a support amount of more than 3.2 billion VND.
This policy aims to create conditions for people to have temporary accommodation, while speeding up the handover of construction sites.
Construction of expressway through Long Thanh district, Dong Nai .
To date, Long Thanh district has approved resettlement for 807/1,700 eligible households. Of these, 709 households have been arranged for resettlement. 87 households are waiting for the lottery. 11 households have not been approved due to disputes or the listing period has not expired. There are 727 cases that are not eligible for resettlement.
Bien Hoa City has handed over nearly 32 hectares, reaching nearly 54% of the total area. The remaining area is waiting for the relocation of assets on the land. In Long Thanh District, with component project 1, more than 62 hectares have been handed over, reaching 80%; component project 2 handed over nearly 138 hectares, reaching 91%.
The Bien Hoa - Vung Tau Expressway construction is being carried out simultaneously at the projects. Specifically, component project 1 is focusing on filling the foundation, casting beams, culverts, drainage systems, overpasses... In component project 2, workers are focusing on making foundations, road surfaces, bridges, intersections, slopes... The total output of the packages is currently about 5-30%.
The entire Bien Hoa - Vung Tau expressway is nearly 54km long through Dong Nai and Ba Ria - Vung Tau provinces, with a scale of 4-6 lanes, with a total investment of 17,800 billion VND. Of which, Ba Ria - Vung Tau is the investor of component project 3, nearly 20km long; the Ministry of Transport is the investor of component project 2, 18.2km long through Long Thanh, Dong Nai; Dong Nai province is the investor of component project 1, 16km long through Bien Hoa city and Long Thanh (Dong Nai).
Currently, the progress of component 1 and component 2 projects is slower than planned due to land clearance and land leveling problems. As for component 3 project, due to having sufficient land, soil, rock, sand, etc., it is more favorable, the output is very good, and it is expected to be open to traffic on April 30, 2025.
Source: https://www.baogiaothong.vn/ho-tro-hon-42-ty-dong-tien-tam-cu-cho-nguoi-dan-giao-dat-lam-cao-toc-bien-hoa-vung-tau-192241130074909794.htm