Vietnam.vn - Nền tảng quảng bá Việt Nam

Nearly 50% of the Ring Road 2 Project in Bac Ha Commune has been completed.

The Ring Road 2 project in Bac Ha commune is one of the key projects prioritized by the local authorities. Upon completion, it will contribute to the completion of a connected transportation network, serving travel needs and promoting socio-economic development. By the end of November 2025, the project had reached nearly 50% completion; many components continue to be implemented with the coordinated efforts of various sectors and the cooperation of the people.

Báo Lào CaiBáo Lào Cai11/12/2025

z7316333637177-911d706b15dbc46946607d3660ae4447.jpg
Many relocated households have begun constructing their homes.

Continue to focus on land clearance.

The Ring Road 2 project in Bac Ha commune, with a total investment of 376 billion VND, affects 471 households in the area. According to Mr. Nguyen Trong Quan, Deputy Director of the Bac Ha Area Investment and Construction Project Management Board, most households have now agreed to receive compensation, and many have received resettlement land and built new houses to hand over the land.

Currently, there are still 30 households in the entire project who have not agreed to the terms, due to various reasons such as procedural obstacles, compensation rates, or difficult circumstances in fulfilling their financial obligations. The Bac Ha Area Investment and Construction Project Management Board and the Commune People's Committee are continuing to disseminate information, persuade, and hold direct dialogues to resolve each case.

Mr. Quan stated: “We are striving to complete all land clearance work by December 31, 2025. The committee always prioritizes public awareness campaigns and fostering consensus among the people to ensure the project's smooth implementation. If the people understand, share, and cooperate, the project will reach its goal sooner.”

baolaocai-c_dji-0958.jpg
baolaocai-c_dji-0961.jpg
baolaocai-c_z7316333738095-ba64b92c0265ec197e176e53cb242dfb.jpg
The construction crew is continuing to excavate and widen the roadbed.

Currently, the project has completed nearly 2 km of the initial route; the final 2.9 km is awaiting land clearance completion. Bac Ha commune has established working groups that regularly visit the grassroots level to monitor developments, explain policies, and ensure that the mobilization efforts are carried out persistently and in accordance with regulations.

The goal is to complete this by 2026.

During implementation, the project encountered numerous difficulties due to rocky terrain, a shortage of fill soil, and the need to adjust the construction plan. Some sections could not be blasted and required manual drilling and excavation, affecting the progress. Furthermore, a representative from the contractor, Anh Nguyen Co., Ltd., stated that the contractor is facing a funding shortage because the state's land auction process has not yet been completed, preventing the allocation of additional funds for the project.

baolaocai-c_z7316339827328-46f1ee41904c92daeed984ce45f85c9c.jpg
Nearly 2 km of the route has been completed with road surface and electricity system to resettle the local people.

Mr. Vu Kim Hai, Director of Anh Nguyen Bac Ha Co., Ltd., stated: “The construction unit is mobilizing machinery and personnel to the best of its ability. Once the project site is prepared and some technical solutions are adjusted, the unit will focus on accelerating the construction progress and completing the remaining tasks.”

On the investor's side, Mr. Nguyen Trong Quan, Deputy Director of the Bac Ha Area Investment and Construction Project Management Board, added: The Board is also requesting Bac Ha commune to add more capable subcontractors to support the construction items, in order to ensure the overall progress. Currently, the project is being considered for an extension, with the goal of completing it in 2026.

baolaocai-c_z7316333679978-352a36314e63cba185e0598bfec5307f.jpg
The contractor mobilized machinery and equipment to carry out the project.

Upon completion, the Ring Road 2 project will create a continuous transportation network, expand urban space, and promote the development of trade, services, and tourism in Bac Ha. Therefore, the joint efforts of all levels of government and the support of the people are of paramount importance.

These days, on the construction site, the construction unit is actively leveling the newly handed-over ground and implementing the road project; the commune's propaganda teams are still persistently going down to the villages and residential areas to explain policies and create consensus among the people.

Source: https://baolaocai.vn/hoan-thanh-gan-50-du-an-duong-vanh-dai-2-xa-bac-ha-post888701.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product