Vietnam.vn - Nền tảng quảng bá Việt Nam

The last days at the construction site of 500kV line circuit 3 in Nghe An

Việt NamViệt Nam24/08/2024


TPO – Ahead of completion, workers on the 500kV circuit 3 power line construction site in Nghe An province are urgently pulling wires and installing equipment to hand over the project to the operation and management unit for energization.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 1)

The 500kV circuit 3 transmission line project from Quang Trach ( Quang Binh ) to Pho Noi (Hung Yen) has a total length of nearly 520km, passing through 9 provinces. The project is invested by the Vietnam National Power Transmission Corporation. The entire line has 1,177 tower locations and 502 spans with a total investment of approximately 22,300 billion VND. After many months of construction, the 500kV circuit 3 transmission line through Nghe An province is gradually being completed.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 2)

In Nghe An province, the project, approximately 100km long, includes 202 tower foundation locations and 85 corridor anchor points, passing through 6 districts and towns: Hoang Mai, Quynh Luu, Yen Thanh, Dien Chau, Nghi Loc, and Nam Dan.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 3)

This is a key, urgent project of paramount importance to national energy security. Along with the 500kV circuits 1 and 2, the completion of the 500kV circuit 3 will play a crucial role and have significant implications for supplying and supplementing electricity to the North.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 4)The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 5)

In the final days of the "final push" phase, workers on the 500kV circuit 3 power line construction sites in Nghe An are urgently pulling the span wires connecting the power poles.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 6)The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 7)

Teams of workers are working diligently to pull wires and install equipment on poles in order to complete the project as soon as possible.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 8)

Coils of electrical cable are continuously transported to the base of utility poles for wiring.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 9)The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 10)

High above, workers had to hang precariously to do their jobs. Despite the scorching heat and the burning hot winds from Laos, the workers persevered at high altitudes to install power lines.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 11)

Mr. Ha Dinh Huy (46 years old, from Tuong Duong district, Nghe An province; residing in Dien Bien province; a worker at Song Da 11 Company) said that the hot weather and strong winds in recent days have made the work of pulling wires and installing power lines difficult. However, with high determination, the workers are still working diligently to complete the project on schedule.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 12)The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 13)

The workers divided the tasks among different teams, working both at height and on the ground, so they had to communicate with each other via walkie-talkies. "We had to constantly look up to coordinate with the workers at the top of the pole to ensure everything was done correctly and accurately. On sunny days, looking up at the sky for even a short time would make our eyes water," shared Quàng Văn Quân (born in 1988, residing in Điện Biên province).

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 14)

The electrical cables are 2,000-2,400 meters long and weigh 5-6 tons, so workers have to use powerful winches to pull them.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 15)

Sometimes, power cables get tangled in obstacles, and electricians have to grope their way through the forest to get them out of the way.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 16)

After long hours of hard work, the workers take a break at the construction site. Some rest, while others use those few minutes to call home and check on their wives and children.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 17)

Mr. Nguyen Van Dung, Deputy General Director of Song Da 11 Joint Stock Company, said that the company has mobilized more than 700 workers from various locations to Nghe An to work during the "final push" phase. To date, the company has basically completed the installation of fiber optic cables and lightning protection circuits on 65 power poles under its responsibility in Nghe An. Simultaneously, they are laying power lines. "We are striving to complete the power line installation by August 25th and energize and inaugurate the project before September 2nd, as requested by the Prime Minister," Mr. Dung said.

The final days on the construction site of the 500kV circuit 3 power line in Nghe An (photo 18)

Thanks to the high level of dedication from the workers, the power poles on the 500kV circuit 3 transmission line are gradually taking shape and nearing completion.

Ngoc Tu

Source: https://tienphong.vn/nhung-ngay-cuoi-cung-tren-cong-truong-duong-day-500kv-mach-3-o-nghe-an-post1666459.tpo


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product