DNO - The People's Committee of Quang Nam province has just issued Official Dispatch No. 3751/UBND-KTN dated May 24, 2024 to the People's Committee of Da Nang city, the Department of Agriculture and Rural Development, the Department of Natural Resources and Environment of Quang Nam province and the People's Committee of Dai Loc district regarding the construction of a temporary dam on the Quang Hue river in 2024.

More than a month ago, Da Nang Water Supply Joint Stock Company opened the road and mobilized trucks to transport materials to Quang Hue dam, but faced with protests from the people, so it has not reinforced or built a temporary dam to a height of 2.3m. Photo: H.H
More than a month ago, Da Nang Water Supply Joint Stock Company opened the road and mobilized trucks to transport materials to Quang Hue dam but did not reinforce or build a temporary dam to an elevation of 2.3m. Photo: HH

Accordingly, the People's Committee of Quang Nam province requested the Department of Agriculture and Rural Development, the Department of Natural Resources and Environment and relevant sectors and agencies of Quang Nam province to coordinate with Da Nang Water Supply Joint Stock Company and relevant sectors and agencies of Da Nang city in implementing the temporary dam construction on Quang Hue river according to the policy of the Provincial People's Committee.

Dai Loc District People's Committee presides over and coordinates with Da Nang Water Supply Joint Stock Company and relevant sectors and agencies of Quang Nam province and Da Nang city to provide information, plans, and plans for implementing temporary dam construction and to propagate and mobilize local people to create consensus for Da Nang Water Supply Joint Stock Company to implement temporary dam construction on Quang Hue river.

Quang Nam Provincial People's Committee requested Da Nang City People's Committee to continue directing Da Nang Water Supply Joint Stock Company and relevant departments and agencies of the city to actively coordinate with Dai Loc District People's Committee and relevant departments and agencies of the province to organize the provision of information, plans and plans for the implementation of temporary dam construction; propagate and mobilize local people and explain related arising issues (if any), creating conditions for the implementation of the construction of temporary dam construction on Quang Hue River according to the set plan.

Previously, more than a month ago, implementing the policy of the People's Committee of Quang Nam province and the People's Committee of Da Nang city, Da Nang Water Supply Joint Stock Company opened the road to gather materials at the site to prepare for construction, reinforcing the temporary dam on Quang Hue river to an elevation of 2.3m, lower than the lowest level of Vu Gia river (2.34m) in the hydrological data series from 1976-2008, before the hydroelectric reservoirs were built (in previous years, the temporary dam was built to an elevation of 3.2m).

However, during the implementation process, local people obstructed the project because they did not receive information about the temporary dam reinforcement. Local people also said that the temporary dam reinforcement would cause erosion and reduce the groundwater source for the wells being used by local people in Dai An commune, Dai Loc district (Quang Nam province), so the company could not carry out the construction for more than a month.

According to the results of hydrological chain statistics from 1976 to 2008 (before the hydroelectric reservoirs on the Vu Gia river basin), the water level of Vu Gia river at Ai Nghia hydrological station (Dai Loc district) was at its lowest point of 2.34m, the average water level of the 3 driest months of Vu Gia river here was 2.67m and the average of the 1 driest month was 2.53m.

Since the hydropower plants on the Vu Gia river basin came into operation, the water level of the Vu Gia river in the dry season has gradually decreased and many times dropped to historic lows, especially in August 2023 at 1.45m and February 2024 at 1.41m.

During the years 2019-2021, based on the agreement of the Coordination Board on the integrated management of the Vu Gia - Thu Bon river basin and the coastal area of ​​Quang Nam - Da Nang, Da Nang Water Supply Joint Stock Company built a temporary dam with sandbags on the riverbed at the Vu Gia river water regulation gate on the Quang Hue river to an elevation of 3.2m.

The new elevation of 3.2m is enough to reduce the water diversion rate of Vu Gia River to Thu Bon River (through Vu Gia River water regulation gate on Quang Hue River) to 24%, equivalent to the previous natural diversion rate before the construction of Dak Mi 4 hydropower reservoir.

HOANG HIEP


Source

Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;