Prime Minister: Assigns "6 clear responsibilities" to accelerate the Lao Cai - Hanoi - Hai Phong railway project.

VTV.vn - The Prime Minister has requested the Lao Cai - Hanoi - Hai Phong Railway Project Management Board to continue promoting the project's implementation as soon as possible.

Đài truyền hình Việt NamĐài truyền hình Việt Nam29/09/2025

On September 29, Prime Minister Pham Minh Chinh chaired a meeting of the Government Standing Committee to hear a report on the results of the first session of the Vietnam-China Railway Cooperation Joint Committee and to review the situation and progress of the work, continuing to promote the implementation of the Lao Cai - Hanoi - Hai Phong railway project as required.

Thủ tướng: Phân công

Prime Minister Pham Minh Chinh chaired a meeting of the Government Standing Committee to hear a report on the results of the first session of the Vietnam-China Railway Cooperation Joint Committee - Photo: VGP/Nhat Bac

Also attending were Deputy Prime Ministers , leaders of ministries, and agencies under the Government.

According to a resolution of the National Assembly, the Lao Cai - Hanoi - Hai Phong railway project, approximately 419 km long with a total capital of VND 203,231 billion (equivalent to USD 8.37 billion), is scheduled to commence in 2025 and be completed by 2030. The Prime Minister has requested that the groundbreaking ceremony for several components of the Lao Cai - Hanoi - Hai Phong railway project be held on December 19, 2025.

Thủ tướng: Phân công

The Prime Minister emphasized the spirit of self-reliance, proactiveness, and initiative, doing what can be done immediately, and continuing to coordinate closely with the Chinese side, persistently exchanging views to achieve the goal. - Photo: VGP/Nhat Bac

After hearing the reports, opinions, and conclusions of the meeting, Prime Minister Pham Minh Chinh highly appreciated the efforts of the ministries and agencies in implementing the assigned tasks. The inter-ministerial working group attended the first session of the Vietnam-China Railway Cooperation Joint Committee, which recently took place in Beijing, China.

The Prime Minister requested relevant agencies to continue implementing high-level agreements as well as the contents reached at the first meeting of the Joint Committee; the spirit is one of high determination, great effort, decisive action, completing each task thoroughly, ensuring synchronicity and comprehensiveness, "what is said must be done, what is committed must be implemented, and what is done must yield concrete, measurable results," and assignments must be clear according to six criteria: clear person, clear task, clear time, clear responsibility, clear authority, and clear output.

The Prime Minister emphasized the spirit of self-reliance, proactiveness, and initiative, doing what can be done immediately, and continuing to coordinate closely with the Chinese side, persistently exchanging views to achieve the goals; ministries and agencies must proactively implement tasks according to their functions, duties, and powers, and cooperate synchronously and closely with each other. If difficulties or obstacles arise that are beyond their authority, they must immediately propose solutions to the competent authorities.

Thủ tướng: Phân công

The Prime Minister requested the Lao Cai - Hanoi - Hai Phong Railway Project Management Board to continue promoting the project's implementation as soon as possible - Photo: VGP/Nhat Bac

The Prime Minister requested the Ministry of Science and Technology and the Ministry of Construction to urgently implement, appraise, and publish the standards and regulations for high-speed railways, specifically the Lao Cai - Hanoi - Hai Phong railway, in accordance with the correct procedures, authority, and legal and international regulations, to be completed by October 2025. The Ministry of Education and Training and relevant agencies should immediately implement cooperation in human resource training. The Ministry of Foreign Affairs should continue to promote high-level activities to facilitate the implementation of projects connecting with China.

The Ministry of Finance, in collaboration with relevant agencies, will review and calculate funding arrangements, proactively securing Vietnamese capital and researching the most effective loan options. Simultaneously, they will continue working closely with the Asian Infrastructure Investment Bank on the feasibility of securing loans for the project. A detailed plan will be urgently submitted to the Government Standing Committee in October.

The Prime Minister requested the urgent strengthening of human resources and the consolidation of railway project management boards under the Ministry of Construction; the Lao Cai - Hanoi - Hai Phong Railway Project Management Board should continue to promote the project's implementation as soon as possible with a spirit of learning as it goes, drawing lessons from experience, and being as proactive as possible in carrying out tasks, especially those that can be done independently.

The Prime Minister instructed the Ministry of Construction and relevant agencies to develop a comprehensive plan for critical path progress, land clearance, and component projects. Specifically, for component project 1 (investment in infrastructure connecting stations along the line and station plazas, using domestic capital), the Prime Minister requested the completion and approval of the feasibility study report by October 2025; the completion of technical designs for the commencement items before November 6th; the selection of contractors and supervisory consultants before December 5th; and the completion of land clearance and bomb and mine removal within the commencement area before December 19th.

Thủ tướng: Phân công

The Prime Minister instructed the Ministry of Construction and relevant agencies to develop a comprehensive plan on critical path timelines, land clearance, and component projects - Photo: VGP/Nhat Bac

Regarding component project 2 (investment in railway construction, using domestic and loan capital), the Prime Minister requested the urgent preparation of a feasibility study report, to be completed no later than June 2026, with the spirit of prioritizing quality above all else; the appraisal and approval of the report must also be carried out urgently.

Regarding the agreement on connecting standard gauge railways between the two countries, the Prime Minister directed that the documentation and technical plan be finalized by September 2025.

Regarding cooperation in railway industry development, the Prime Minister emphasized the approach of implementing projects from low to high levels, from small to large, from simple to complex, ensuring thoroughness at each stage.

The Prime Minister requested the Ministry of Construction to continue to do a good job in leading and coordinating cooperation with China, building on the achievements already made, developing a roadmap, progress and specific work contents in the spirit of "6 clear points", and reporting periodically every month; along with the Lao Cai - Hanoi - Hai Phong railway project, it must continue to promote the Dong Dang - Hanoi and Mong Cai - Ha Long - Hai Phong railway projects connecting Vietnam and China.

Source: https://vtv.vn/thu-tuong-phan-cong-6-ro-de-thuc-day-du-an-tuyen-duong-sat-lao-cai-ha-noi-hai-phong-100250929214210769.htm


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.
The unforgettable beauty of shooting 'hot girl' Phi Thanh Thao at the SEA Games 33
Hanoi's churches are brilliantly lit, and the Christmas atmosphere fills the streets.
Young people are enjoying taking photos and checking in at places where it looks like "snow is falling" in Ho Chi Minh City.

Same author

Heritage

Figure

Enterprise

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree

News

Political System

Destination

Product