
The Corporation has directed power companies (PCs) to deploy disaster response plans, mobilize 100% of on-duty personnel, quickly assess damage, localize incidents, and mobilize adequate materials and equipment to restore the power grid.
In Thai Nguyen, about 8,300 customers had their electricity interrupted. Thai Nguyen Electricity Company mobilized 100% of its staff to be on duty and urgently handle the power grid problem.

Ninh Binh Electricity Company said that 86 medium voltage lines were affected, of which 47 lines have been restored, and 39 lines are still being inspected and processed.
The power grid in some communes of Lac Son, Luong Son, Lac Thuy, Hoa Binh , Phuc Yen, Tam Duong (Phu Tho province) recorded damage with 22 medium voltage lines having incidents, 3 poles broken...

In Thanh Hoa, according to preliminary statistics, the heavily affected areas include Bim Son - Ha Trung, Hoang Hoa and Cam Thuy with dozens of electric poles having problems such as broken, broken wires...
Source: https://hanoimoi.vn/tren-100-000-khach-hang-bi-gian-doan-su-dung-dien-sau-giong-loc-709712.html
Comment (0)